Find the values at the end of week four

Assignment Help Project Management
Reference no: EM132352570

Project Scheduling and Cost Planning Assignment - EVM

Instructions: You are the project manager of a software development project. The team members will be working on five different components. Each of the components is budgeted to be $2,625, and all components are supposed to be completed in five weeks. Using the status in the following table, find the following values at the end of week four.

Project

Planned End Date

Planned Budget

Actual Amount Spent by Week Four

Planned Completion by Week Four

Actual Completion by Week Four

Software Development Project

End of 5th week

$13, 125 for total project or $2,625 for each component

$9,000

Four out of five components

Three out of five components

 

Acronym

Term

Formula

Answer

Interpretation

PV

 

 

 

 

EV

 

 

 

 

AC

 

 

 

 

SV

 

 

 

 

CV

 

 

 

 

CPI

 

 

 

 

SPI

 

 

 

 

BAC

 

 

 

 

EAC

 

 

 

 

ETC

 

 

 

 

VAC

 

 

 

 

TCPI

 

 

 

 

Requirements:

  • Use this MS Word file to complete your assignment and submit via Blackboard.
  • Save your files using the following filename convention: EVM - FirstName_LastName.

Be sure to read the criteria, by which your paper/project will be evaluated, before you write, and again after you write.

Reference no: EM132352570

Questions Cloud

What is the approximate doubling time of culture : Your Clan performs the growth curve experiment from Lab 2 with a newly discovered bacterium, and records the following Data for your Growth Curve Experiment:
Discuss the role of state-based action coalitions : Discuss the role of state-based action coalitions. Explain how these coalitions help advance the goals specified in the IOM report, "Future of Nursing.
Discuss the epidemiologic triangle you have selected : Discuss the epidemiologic triangle as it relates to the communicable disease you have selected. Include the host factors, agent factors (presence or absence).
What are your opinions on monogamous relationships : After watching Ted Talks video and what you learned throughout the class regarding gender and sexuality in today's modern world, what are your opinions.
Find the values at the end of week four : PMG640 - Project Scheduling and Cost Planning Assignment - EVM, The Malcolm Baldrige School of Business, Post University, USA. find the values at end of week
What are some of new constructs that nurses are integrating : What are some of the new constructs that nurses are integrating in promoting the health of communities? Write a 300 - word paper using APA Format.
Write down the community response to teaching : The written portion of this assignment should include: Community response to teaching. Prepare this assignment according to the APA guidelines found in the APA.
Identify and evaluate the initial steps : International Diploma in Financial Crime Prevention - Evaluate the importance of inter-government cooperation and the use of mutual legal assistance treaties
Large marks on the stage micrometer : How many microns (µM) is one ocular unit in the 10X objective?

Reviews

len2352570

8/5/2019 10:38:43 PM

Evaluation Rubric for EVM Assignment- Justifications for reserve fund are based on clear estimations using EMV calculations and or PERT. The estimations are complete and matches the justifications. All activities are Sequenced using the predecessors’ column with a closed network diagram. At least 4 of your tasks relationships must be different than Finish to Start. Cost baseline include all activity cost estimates and when added up equals the cost baseline and contingencies. Summary budget fully updated to include cost baselines estimates.

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd