Find the expected completion time of all eight jobs

Assignment Help Engineering Mathematics
Reference no: EM131469502

Question: A computer center has two identical computers for batch processing. The computers are used as parallel processors. Job times are estimated by the user, but experience has shown that an exponential distribution gives an accurate description of the actual job times. Suppose that at a point in time there are eight jobs remaining to be processed with the following expected job times (expressed in minutes):

Job                       1              2             3              4               5              6              7              8

Expected time       4              8             1             50               1             30            20              6

a. In what sequence should the jobs be processed in order to minimize the expected completion time of all eight jobs (i.e., the makespan)?

b. Assume that computer A is occupied with a job that has exactly two minutes of processing time remaining and computer B is idle. If job times are deterministic, show the start and end times of each job on each computer using the sequence derived in part (a).

Reference no: EM131469502

Questions Cloud

Truth based sales culture : "Truth based sales culture". What is the importance of this? please explain with an example
Prepare three sigma controlchart for both production process : Prepare a three-sigma control chart for both production processes, using the new and standard material.
How should they plan schedule in order to minimize time : Peter Minn is planning to go to the Department of Motor Vehicles to have his driver's license renewed. His friend, Patricia, who is accompanying him.
What is the standard deviation of the production : The amount of milk produced by dairy cows depends on number of factors, including average temperature and rainfall. What is standard deviation of the production
Find the expected completion time of all eight jobs : A computer center has two identical computers for batch processing. The computers are used as parallel processors. Job times are estimated by the user.
Separation of powers affect administrative decision making : In what ways does the separation of powers affect administrative decision making? Does it promote the rational-comprehensive approach, incrementalism,
Evaluate the factors of demand and supply : FINA3324 Investment Analysis: "Buy or rent?" Assignment. Evaluate the factors of demand and supply that will cause house and rent prices to fluctuate
The operations are in parallel : A product needs to go through only one of the three assembly operations? (the operations are in parallel).
In what sequence should the ships be unloaded : Six ships are docked in a harbor awaiting unloading. The times required to unload the ships are random variables with respective means of 0.6, 1.2, 2.5, 3.5, 0.

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Indicate the polarity by proper placement of the symbols

Draw structural formulas for all possible isomers having the following molecular formulas

  Problems based on the hypothesis testing process.

Do the sample data indicate a significant change in depression (2-tailed test)? Test with alpha = .05, 2-tailed test

  Solve problem graphically or by using the simplex iterations

Which syrup type do you recommend to be increased? Why - Suppose that the daily amount of syrup 1 is increased to 280 gallons. How much will this change contribute to the optimal profit?

  Calculate the volume of the rock

When the elevator is at rest, the tension in the cord is 21.0 N. Calculate the volume of the rock. Derive an expression for the tension in the cord when the elevator is accelerating upward with an acceleration of magnitude a. Calculate the tension ..

  Health counselors with doctoral degrees

Do mental health counselors with doctoral degrees earn a higher yearly income than those with masters degrees 5 years post graduation? Provide the IV, DV, Covariate, and best method of analysis.

  Compute by hand the mean and standard deviation

Question 1: The following data set shows the amount of time consumers have to wait on hold, in minutes, before talking to a customer service representative. Compute by hand the mean and standard deviation. Take a picture, scan your work, or type u..

  Manufacturer of several different cheese products

Megley Cheese Company is a small manufacturer of several different cheese products. One of the products is a cheese spread that is sold to retail outlets.

  Kind of t-shirt should the club order

It will sell "ordinary" T-shirts at profit of $4 each, "fancy" T-shirts at profit of $5 each, and "very fancy" T-shirts at a profit of $4 each. How many of each kind of T-shirt should the club order to maximize profit?

  Swiss franc and the australian dollar

A bank is quoting the following exchange rates against the dollar for the Swiss franc and the Australian dollar:

  Find the inverse transform

Find the inverse transform and find the Laplace transform - Express the following function in terms of unit step functions

  Find the mean mode and median investment

Survey at least 30 engineering students to obtain each student's total investment in calculators and computers in the past 18 months.

  The explanatory and response variables

Compute the value of the correlation coefficient (r). (This computation may be done using your calculator or computer.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd