Explain the project performance in terms of efficiency

Assignment Help Project Management
Reference no: EM13782107

Explain the project performance in terms of efficiency, budget and schedule. What should the project manager do for the project?

In terms of performance, the project is not cost-efficient, over budget by $72, is behind schedule 57 days, and not time efficient. The project manager should review the variances since the cost and schedule variances are negative. The negative numbers mean something is wrong or missing and/or the efforts of those involved have been incorrectly calculated. The numbers ought to be redone to get the correct answers. Thus, the project is not cost- or time efficient at this time. The project manager must come up with new project deadlines and a new budget to ensure guidelines meet properly and are in line with the project budget.

Reference no: EM13782107

Questions Cloud

Sensation and perception are two different processes : Sensation and perception are two different processes. Does sensory stimulus shape our perceptions? Do our perceptions misinterpret our sensations? How does that happen?
What stage of kohlbergs moral reasoning is best : What stage of kohlbergs moral reasoning is best associated with gillians morality of care?
Determine the optimal size of the shopping center : Determine the optimal size of the shopping center (to the nearest 100 square meters) based on existing estimates of the demand for retail space.
Customer also specifies that blend should be mixed in ratio : The Tennessee Jack Distillery produces custom whiskey. A particular blend consists of rye and bourbon whisky. The company has received an order for 400 gallons of the custom blend... The customer specified that the order must contain at least 40 perc..
Explain the project performance in terms of efficiency : Explain the project performance in terms of efficiency, budget and schedule. What should the project manager do for the project
Key factors involved in assessing the amount of trust : If you were in a position to persuade another person, explain whether or not you would slant information in such a way as to make your point seem more credible if you sincerely believed that your position was correct. Discuss the primary ethical d..
Toying with success : Individual assignment: McFarlane Case, p. 65 (Manning & Curtis): "Part One Video Case, Toying with Success: The McFarlane Companies"After reading the case, answer "Questions for Discussion" 1 and 2, providing evidence for points you make.Then, includ..
Review the genetic information nondiscrimination act of 2008 : REVIEW the Genetic Information Nondiscrimination Act of 2008 (GINA). Then, review the following Nondiscrimination Act Case Studies.
Design and graphics issues : Explain why it is useful and what it means in the context of your Final Project. Be sure to reference relevant material.

Reviews

Write a Review

Project Management Questions & Answers

  Project management plan dear experti have attached word

dear experti have attached word file please have a look and read carefully about the requirements i need good wok with

  Module is to select an organization for your project you

module is to select an organization for your project. you may consider any of these organizations as long as you have

   capstone project preliminary literature review and action

details ltbrgtthis assignment comprises two sections a preliminary literature review and an action item checklist.

  Evaluate vendors proposals for a project

Prepare a project plan that covers all project groups and knowledge areas and develop project plans that integrate project procurement and contracting activities across project groups.

  Total carrying cost per yearif it costs 2 in storage costs

total carrying cost per yearif it costs 2 in storage costs to hold a 10 item in storage for 1 year the total carrying

  Question about production budgetemerson company makes

question about production budgetemerson company makes surfboards. each surfboard requires 9 pounds of fiberglass to

  Project management and changeyou have been assigned to

project management and changeyou have been assigned to project manage the opening of a new restaurantexplain what kinds

  Annual holding costfredericks farm factory fff currently

annual holding costfredericks farm factory fff currently marintains an average inventory valued at 3400000. the company

  Importance of incorporating a budget into project schedule

Explain the importance of incorporating a budget into a project schedule.

  Project in international business course

Project in International Business course

  Presentation for senior management outlining

Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan

  Assistance on project management

How would you proceed and what tools would you use - when was a time that a situation like this was handled successfully

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd