Assignment: Project Schedule Changes

You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.

You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.

In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.

Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.

You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.

You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.

Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.

Attachment:- Project-Plan-Check-District-Move.rar

Reference no: EM131704604

Questions Cloud

What tactics can you implement to strengthen a multi-party : What tactics can you implement to strengthen a multi-party coalition
Define proprietary-type funds and accounting measurements : State whether the following sentences are true or false regarding proprietary-type funds and the accounting measurements made within them.
Compute the total cost of making and buying the parts : The segment margin of the new product would be $150,000 per year. Compute the total cost of making and buying the parts
Discuss the nature of fiduciary-type funds : State whether the following sentences are true or false regarding the nature of fiduciary-type funds and the accounting measurements within them.
Explain best course of action for bringing warehouse project : Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation
What the buyers personal situation is : How the stroller and its package make it easy to store, display and carry .What the buyer's personal situation is (tenure, pending retirement, etc.).
Discuss difficult to embrace with a fluid or growth mindset : What 5 key principles of effective differentiation and will be the most difficult to embrace with a fluid or growth mindset
Measurement focus and basis of accounting for different fund : Several new city council members asked you to explain why the financial statements for the Water Enterprise Fund "seem to look different" than the financial.
Nature of governmental fund types and fund balances : J. J. Peachum is running for election as a commissioner of the municipality of Mt. Lebanon. He examines Table in the text and calculates the total.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd