Evaluate the number of surfboards

Assignment Help Project Management
Reference no: EM1343625

Question about Production Budget

Emerson Company makes surfboards. Each surfboard requires 9 pounds of fiberglass to produce. The sales forecast for March is 1,700 surfboards. Estimated beginning and desired ending inventories for March are the following:

Estimated Beginning Inventory Desired Ending Inventory
Surfboards 300 420
Fiberglass (pounds) 4,400 6,000

a) Evaluate the number of surfboards to be produced in March.

b) Evaluate the number of pounds of fiberglass to be purchased in March.

Reference no: EM1343625

Questions Cloud

Possibility of unforeseen restraints cropping up : What steps can a project manager take to minimize the possibility of unforeseen restraints cropping up in the middle of a project?
Points of the project scope checklist : Briefly explain the first five points of the Project Scope Checklist in relation to your project and What are the project objectives?
Describe a concise clear and measurable plan : Identify and describe a concise clear and measurable plan to monitor the human change elements of the Target project.
Provide an example of a project : Provide an example of a project that is driven by each of the following needs
Evaluate the number of surfboards : Evaluate the number of surfboards to be produced in March and evaluate the number of pounds of fiberglass to be purchased in March.
Evaluate the expected npv : There is a 40 percent chance of average demand, with cash flows of $30 million per year and cash flows will be only $15 million per year. What is the expected NPV
Low-performing employees : Avoid that risk, what Organizational policies might encourage low-performing employees to leave while encouraging high-performing employees to stay?
Fixed-price and cost-plus contracts : Can teams be used for both fixed-price and cost-plus contracts and is there a difference in how teams work based on the contract being fixed-price or cost-plus contracts?
What can you do to eliminate the risk : What is impacted if this risk occurs? What is the extent of the impact and what can you do to eliminate the risk

Reviews

Write a Review

Project Management Questions & Answers

  Managing the project

As part of your project to assess the security risks for computing the infrastructure, you have found that the other managers often have different ideas on the severity.

  Show the cash flow at time zero

Cash Flow at Time Zero - Which of these should be included in the cash flow at time zero?

  Question about financial systems

Explain what are the economic functions financial intermediaries perform and what is the role of broker in the financial market

  Capital attributable to the project

Current rental income of a building owned by the firm if it is not used for this project and the decline in sales of an existing product directly attributable to this project.

  Amount to use as annual sales figure when evaluating project

This extension would cost $1 million. If annual revenues for Shoe-tek total $80 million, what is the amount to use as the annual sales figure when evaluating this project? Why?

  Improving quality can lead to reduced costs

Explain how improving quality can lead to reduced costs.

  Create a risk identification checklist

Create a risk identification checklist, and  Update risk management documents.  Procedure

  Participate in management and entitled to compensation

Lynda will be allowed to participate in management and is entitled to compensation.

  Critical path and duration of the project

What are the critical path and duration of the project?

  Importance of project sponsorship and leadership

Describe the importance of project sponsorship and leadership when it comes to escalating decisions during a project.

  Evaluate the appropriate opportunity cost of capital

First, Forecast the cash flows generated by project X over its economic life. Second, evaluate the appropriate opportunity cost of capitalr

  Multicultural management in virtual project setting

Write a proposal for multicultural management in the virtual project setting.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd