Evaluate Status of a Project Based on Assigned and Actual Work

Budgeted Work/Cost (PV)
Actual Cost to date (AC)
% work completed
Estimate to complete
Planned start & end dates - Start is Jan. 1, End is April 30
Actual start date - Feb. 1
Projected end date
Planned Resources Utilized - 30%
Actual Resources Utilized - 45%

With the Cost one calculates PV EV and AC.

What I do not understand is when I have dates and planned and actual resources, the formula concerning schedule and cost refers to the financial data but when there are only dates how does that calculation go?

Reference no: EM13363052

Questions Cloud

Assistance on project managementyour manager needs your : assistance on project managementyour manager needs your assistance on a major project. he has asked you to set up a
Persuasive memo starting a company citizenship : persuasive memo starting a company citizenship projectcongratulations youve recently been hired as a public relations
Cost and time methodsas a project manager discuss the cost : cost and time methodsas a project manager discuss the cost and time methods you would chose to work with and why you
Evaluating vendors proposals for a projectat times a : evaluating vendors proposals for a projectat times a project manager must evaluate proposals from identified vendors
Evaluate status of a project based on assigned and actual : evaluate status of a project based on assigned and actual workbudgeted workcost pvactual cost to date ac work
A common assumption following the completion of a project : a common assumption following the completion of a project would be that the sun would rise the next day. suppose for a
Characteristics of high-performing project management : characteristics of high-performing project management teamswhat are the four most important characteristics of
Project management closeout checklistprepare a closeout : project management closeout checklistprepare a closeout checklist for a project including details on what steps you
Change management in a projectdescribe the concept of the : change management in a projectdescribe the concept of the change management process within a project and give two

Reviews

Write a Review

Project Management Questions & Answers

  Basic service blueprint for ebags current product line

Develop a basic service blueprint for eBAGS' current product line. After analyzing your blueprint, would you recommend to eBAGS managers that they consider business process reengineering?

  The proper interpretation of these numbers

the following is the proper interpretation of these numbers? The mean of the production process has shifted to the left of the design limits

  Show the most efficient arrangement possible

Is this the most efficient arrangement possible? Would it be more efficient if more firms could produce Vista?

  Purpose of a project manager

Purpose of a project manager - Why are projects manager in such demand and what type of person do you think could be a PM

  Computing npv of project

None of the projects requires or precludes any of the other projects, and each project costs $2,000. What is the NPV of each project?

  Responsibility of project manager-matrix-type organization

What are the responsibilities of a project manager in a matrix-type organization? What about project-type organizations?

  Find the communication plan

The first step in building a communication plan is to identify your key stakeholders. How would one identify a key stakeholder?

  What is emotional intelligence

What do the letters INTJ stand for in a Myers-Briggs personality profile? Working with People on Projects. Normal 0 false false false EN-US X-NONE X-NONE MicrosoftInternetExplorer4

  Define a project and describe its characteristics

Define a project and describe its characteristics and What are the necessary competencies and skills of a project Manager?

  Create weeklong work schedule to meet needs of employee

Create a weeklong work schedule to meet the needs of the employees, the customers, and therestaurant.

  Describing consensus on the scope of project

Discuss and come to a consensus on the scope of the project, including the major deliverables and the items that are not part of the scope.

  Steps to ensure flawless execution of business strategy

Analyze how HR can be used effectively to work cohesively with an organization's business strategy and explain what steps you could take to ensure flawless execution.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd