Network Diagrams are often used during project planning to give the project manager a visual map of the key activities of the project. Activity-On-Arrow (AOA) is often used to demonstrate the concept of activity sequencing.

Activity

Initial node

Final node

Duration estimate

A

1

2

2

B

2

3

2

C

2

4

3

D

2

5

4

E

3

6

2

F

4

6

3

G

5

7

6

H

6

8

2

I

6

7

5

J

7

8

1

K

8

9

2

Consider Figure the attachment to answer the following questions. All duration estimates are in days, and the network proceeds from Node 1 to Node 9.

1. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.

2. Identify all the paths on the network diagram and note how long they are, using Figure 152) as a guide for how to represent each path.

3. What is the critical path for this project and how long is it?

4. What is the shortest possible time it will take to complete this project?

5. Examine the network diagram and task schedule table to analyze the critical path and float or slack for each activity.

Write at least a paragraph that interprets this information for someone unfamiliar with project time management.

Reference no: EM13962961

Questions Cloud

Nutritional elements per pound of feed : A farmer can purchase 3 kinds of feed for his stock, with various percentages of each of 4 nutrients, called A, B, C, and D.  A mixture of feeds gives proportional amounts of nutrients.  The following table gives the minimum da..
The triangle has the angles 45,45,90 with a base of length : The triangle has the angles 45,45,90 with a base of length a. The dipole is located at the right base corner pointing in the -x direction.
How many trades must he made to break even : Use the contribution margin ratio CVP formula to compute Big Time's break even revenue in dollars. If the average trade leads to $800 in revenue for Big Time, how many trades must he made to break even?
Annual production capacity : The Sentry Lock Corporation manufactures a popular commercial security lock at plans in Macon, Louisville, Detroit, and Phoenix.  The per unit cost of production at each plant is $35.5, $37.5, $39, and $36.25, respectively, while the annual product..
Draw an aoa network diagram representing the project : Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
Small businesses are undercapitalized : Suppose that 30% of all small businesses are undercapitalized. Forty percent of all undercapitalized small businesses fail and 20% of all small businesses that are not undercapitalized fail. A small business is chosen at random. The probability th..
Describe your company operations and the market : For the company you selected, describe your company's operations and the market in which it operates. Search for the EVA, and free cash flow using the firm's annual report
Discuss the signal a large stock repurchase might foretell : Discuss the signal a large stock repurchase might foretell about management's outlook relative to the future of a company. Explain whether a repurchase of stock is typically a good or bad sign. Provide a rationale for your response
Understand and measure doppler shift : Now test this out. Move to the distance away from the tuning fork you calculated above. How would you describe the loudness of the sound now? Would you say it is twice as loud?

Reviews

Write a Review

Project Management Questions & Answers

  Show the organizational culture and project management

How does organizationl culture influence the selection, sponsorship, and prioritization and ultimate success of projects

  Reviews of some aspects related in post-tender negotiation

Reviews OF some aspects related in post-tender negotiation and thought on the current procurement policy is effective and appropriate while dealing with procurements for public projects.

  Construction of a shopping center

A principal hired a mortgage banking firm to obtain a loan commitment of $10,000,000 from an insurance company for the construction of a shopping center.

  Work breakdown structure of a projecthow and why you would

work breakdown structure of a projecthow and why you would use a wbs in a project and no particular project just got

  Create a project transition plan

When a project is ready to be deployed, a transition plan can help the transfer of ownership from the project team to the customer or organization that requested the project. Complete the following: For the given scenario, create a project transiti..

  Cost of production report using fifo

Prepare a cost of production report for July using the FIFO method of the process costing - Cost of production report using FIFO

  Complete your portfolio project assignment

Complete your Portfolio Project assignment, focusing on making sure that you have all of the necessary components as set forth in the rubric. Spend time making sure that the formatting meets SEU APA standards, and thoroughly proofread and grammar-che..

  Risk control planningnew markets will gather data from

risk control planningnew markets will gather data from internet chat rooms online news releases and many other sources.

  Discuss the before-during-after aspects of calling

A  discussion board due. The topic is as follows: Topic: Calling Resilient Warriors talks at length about the importance of "calling." Discuss the Before-During-After aspects of "calling," and relate this to your Particular vocation

  How are these different from those in europe

What cultural challenges are posed by Disney's expansion into Asia? How are these different from those in Europe?

  Yorkshire house foods ltd. project orion

A project plan, created using Microsoft Project software, showing a network of tasks, the critical path, human resources required and expected completion times. Use a start date of November 3rd 2014. You must also provide, in text, your appraisa..

  Propose research project

ake a research project to address this problem that focuses on the kind of research design you would use.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd