Draw a gantt chart of the schedule for this project

Assignment Help Engineering Mathematics
Reference no: EM131469519

Question: A project consists of seven activities. The precedence relationships are given in the following table.

Activity                         Time                     Immediate

                                      (days)               Predecessors

A                                32

B                                21

C                                30

D                                45                     A

E                                26                    A, B

F                                28                      C

G                                20                    E, F

a. Construct a network for this project.

b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.

c. Draw a Gantt chart of the schedule for this project based on earliest starting times.

d. What group of activities will have to be completed by day 60 in order to guarantee that the project will not be delayed?

Reference no: EM131469519

Questions Cloud

Determine the immediate predecessors of each activity : Determine the immediate predecessors of each activity from the network representation. Redraw the network based on the results of part (a) with only two pseudo.
Argument for giving space for advertising : According to Goldman, which of the following is NOT an argument for giving space for advertising.
Global trends and global cultures of organizations : For this discussion, explain why it is important for innovation leaders to understand global trends and global cultures of organizations.
About your own experiences regarding creativity : What insights do you have about your own experiences regarding creativity, either in your current or past work environments?
Draw a gantt chart of the schedule for this project : A project consists of seven activities. The precedence relationships are given in the following table. Construct a network for this project.
Challenges to greater sustainability posed by the tragedy : What are the challenges to greater sustainability posed by the tragedy of the commons?
What overall message do you believe the ad is communicating : What overall message do you believe the ad is communicating? Describe what you like about the ad and what could be better. Explain why.
Describe meaning of behavioral obstacles to supply chain : Describe the meaning of behavioral obstacles to supply chain (SC) coordination,
What is the minimum project time and the total direct cost : Consider Example presented in this section in which the two programmers are to develop a commercial software package. What is the minimum project time?

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Prime number theorem

Dirichlet series

  Proof of bolzano-weierstrass to prove the intermediate value

Every convergent sequence contains either an increasing, or a decreasing subsequence.

  Antisymmetric relations

How many relations on A are both symmetric and antisymmetric?

  Distributed random variables

Daily Airlines fies from Amsterdam to London every day. The price of a ticket for this extremely popular flight route is $75. The aircraft has a passenger capacity of 150.

  Prepare a system of equations

How much money will Dave and Jane raise for charity

  Managing ashland multicomm services

This question is asking you to compare the likelihood of your getting 4 or more subscribers in a sample of 50 when the probability of a subscription has risen from 0.02 to 0.06.]  Talk about the comparison of probabilities in your explanation.

  Skew-symmetric matrices

Skew-symmetric matrices

  Type of taxes and rates in spokane wa

Describe the different type of taxes and their rates in Spokane WA.

  Stratified random sample

Suppose that in the four player game, the person who rolls the smallest number pays $5.00 to the person who rolls the largest number. Calculate each player's expected gain after one round.

  Find the probability density function

Find the probability density function.

  Develop a new linear programming for an aggregate production

Linear programming applied to Aggregate Production Planning of Flat Screen Monitor

  Discrete-time model for an economy

Discrete-time model for an economy

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd