1. Using the 50-50 Rule, what is earned value for this project?
2. Using the 0-100 Rule, what is earned value for this project?
Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.
Budget
Begun?
Complete?
Actual cost
Earned Value
Task A
3,100
Yes
Task B
4,000
4,500
Task C
2,500
2,250
Task D
No
3,500
Task E
Task F
0
Prepare a Flexible Budget Gator Divers is a company that provides diving services such as underwater ship repairs to clients in the Tampa Bay area.
This assignment has two question related to maths. Questions are related to bifurcation cascade and logistic map.
This assignment has questions related to probabiltiy.
Find all the xed points, and study their stability and Draw the phase portrait of the system, as well as the graphs of the solutions in all relevant cases.
Derive the Boolean Expression and construct the switching circuit for the truth table stated
Evaluate which equations are under-identified, just-identified, and over-identified.
Linear programming problem consisting of only two constraints with one objective function.
Find the natural domain of the given functions.
Compute the coecients of the polynomials using the term recurrence relation.
De?nition of smoothness of functions on a smooth manifold is chart independent and hence geometric.
Questions related on mathematics in computing.
Complex problems
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd