Determine training objectives

Assignment Help Project Management
Reference no: EM131044009

You are working with your team leads to create the project schedule. You are very concerned about the intersections between the teams, so you all are starting with the major milestones and working backward from the new product launch.

Sales of the new product are going to start in 9 months and the new CRM system needs to be in place 6 weeks prior so the sales force can get their customer and prospect information entered in time for the big marketing mailing going out 3 weeks prior to the product being available. You have one team working on the marketing program (and the mailing is just one of their deliverables); this team is being led by Jennifer from marketing. You also have another team working on the CRM implementation being led by Ben from IT. The two teams will intersect at the sales force training on the new system, the new product, and the new marketing program. After talking with the sponsor and customers, it was determined that the training approach would be holistic; the marketing process would be taught using the new system-not two separate classes, but one integrated class. Instructors will come from both the IT and the marketing teams. You are unsure which team leader should be responsible for training; it will depend upon the resources and dependencies.
Using the list of tasks below as a starting point, create a schedule by adding tasks, dependencies, efforts, and descriptions of the skills required to complete each task. Also, determine the start and end dates based on the dependencies and effort (assume your resources have 50% availability to the project). The schedule should contain between 30 and 60 tasks/subtasks.

Please use Microsoft Project and Word to document your schedule. You will also need to define the team members you will need.

For each team member create a bulleted list of skills and expertise that he or she must have to complete the assigned tasks.
For the effort, describe the rationale for your estimate.

List of Tasks to Be Used:

• Determine training objectives.

• Create training outline (objectives, phases, topics, and content).

• Define activities.

• Create instructor guide.

• Create participant materials.

• Create activity guide.

• Review training materials.

• Conduct pilot training class/test training materials.

• Deliver training to all of sales force.

Reference no: EM131044009

Questions Cloud

Maturing debt responsibilities : When it was time for the country to roll over its maturing debt responsibilities, a limited number of investors were interested in buying new debt. In order to repay tesobonos, the CBM had limited option but to buy dollars using its severely weake..
Mean of data was centered between specification limits : You are evaluating the capability of a process. Standard deviation(s) is 5. Customers have said that they will accept units ranging between 35 and60. The location of the mean isunknown. But your boss wants to know ifthe process is capable of per..
What is the marginal cost of a string : What is the marginal cost of a string at 2 million strings of production level? Assuming that one month is considered a short run, is the firm's decision to produce 2 million strings of licorice this month right or wrong
Process centering relative to the specification : Need a reason for your answer Cp and Cpk are correctly stated as: A.) Cp is for comparing dispersion relative to the specification. Cpk is for comparing process centering relative to the specification
Determine training objectives : List of Tasks to Be Used: Determine training objectives. Create training outline (objectives, phases, topics, and content). Define activities
Process results from combination of input factors : Theoutput of a process results from the combination of input factors such as man, machine, material, methods, measurements, and mother nature.  This list of input factors is MOST COMMONLYused as an aid in the analysis in which Six Sigma tool?
Explore a computer systems general information : Explore a computer system's general information, create a folder on the desktop of the computer, and explore processes that are actively running.
Question regarding the production management : The staff training center at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 1200 employees per year
Present your findings of the above data in a table : Present your findings of the above data in a table. Add a paragraph that summarizes your results, indicating whether investors would find the financial analysis results of Apix competitive as compared to rivals in the sector. Be sure to include bo..

Reviews

Write a Review

Project Management Questions & Answers

  Constraining factor in semiconductor division

What is the constraining factor in the Semiconductor Division?

  Problem-solving and is-building model

Your task is to use Laudon & Laudon's Four-Step Problem-Solving & IS-Building Model and/or the Integrated Framework for Describing and Analyzing Information Systems

  Finding maximum price that company willing to pay

If IRR is 15%, would you please tell me how to find out the maximum price that the company would be willing to pay for the new equipment? Ignore taxes.

  Identify the strategic change proposed

The Project Management Plan should clearly identify the strategic change proposed, expected outcomes, key milestones and deliverables, and prepare the first status report for the project.

  Factors that lead to the effective management of projects

Describe the factors that lead to the effective management of projects and Explain how projects, programs, and portfolios help organizations coordinate their work and meet objectives

  Sony is losing revenue to music pirating

Sony is losing revenue to music pirating. To prevent further illegal copying of its music CDs, Sony has begun placing a software program called Rootkit on its music CDs

  Brief description of how you expect to measure the success o

Prepare a project plan: Description, mission, scope, measurement, management - brief description of how you expect to measure the success of the project

  Objectives for a pro shop in a football stadium

Project Goals and Objectives - Explain what are the Project goals and Objectives for a pro shop in a football stadium.

  Question about systems analysisprepare a paper that

question about systems analysisprepare a paper that analyzes an it work-related project or fictitious project using

  Work breakdown structure differ from the project network

How does the Work Breakdown Structure differ from the Project Network (Diagram)?

  Managing the project

As part of your project to assess the security risks for computing the infrastructure, you have found that the other managers often have different ideas on the severity.

  During the execution of the project

During the execution of the project, it becomes obvious to you that the chief project engineer is making decisions that do not appear to be in the best interest of the project. What should you do about this?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd