Determine the planned project duration

Assignment Help Project Management
Reference no: EM133061811

Learning Activity: Critical Path in a Project Network

Question 1: K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software Project:

2138_Software Project.jpg

Question 2: A large Southeast city is requesting federal funding for a parkand-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. Show your project network with the activity early, late, and slack times. Mark the critical path.

1614_Software Project1.jpg

Question 3: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project Page 194 network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.

2207_Software Project2.jpg

Reference no: EM133061811

Questions Cloud

Allocate the cost of advertising : Do you agree with TRU's decision not to allocate the cost of advertising? Why or why not? Be specific about any alternative allocation methods that you would co
Allocate the building-related costs : Would you recommend that TRU continue to allocate the building-related costs only to the preschool program? What alternative allocation method would you Suggest
Investment earn on an annualized basis : 1. Your grandfather gave you a stamp originally issued in 1955, that he bought for 20 cents in that year. But after searching through the internet, you find th
Prepare all entries required on the preceding dates : The machine originally cost $26,000 and accumulated depreciation was $12,000 when it was sold. Prepare all entries required on the preceding dates
Determine the planned project duration : Determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers
How will each of the options above affect EPS : How will each of the options above affect EPS, DPS, WACC and TIE assuming each option is independent of the other and the rest of the data is the same
What is the expected rate of return on a project : What is the expected rate of return on a project that requires an investment of $106 today and generates cash inflows of $7, $17 and $122 in each of the next 3
Determine the market price per share after the split : Question: (a) A project has an unlevered Net Present Value (NPV) of RM1.5 million. To finance the project, debt is being issued with associated flotation costs
Calculate the profit-loss for the four positions : At the close of Friday (Nov 13th), NIO is trading at $44. If you look at the call options that expires next Friday (Nov 15th) with a strike price of $45, $48, a

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd