Determine the overall cost of and time for the project

Assignment Help Project Management
Reference no: EM13903324

Management Assignment : Project management-plan

You are a project manager in the IT department of a company. You have been asked to develop a customised software application for the sales department of your company. You have already gathered the requirements, documented the specifications, and developed a project schedule. The head of the sales department wants the user interface of the software to be generated early in the project so that she can provide feedback that will enable you to make adjustments to the user interface. After seeing the user interface, the head of the sales department suggests a number of changes and some new features to be added to the software.
On the basis of the project information, complete the following tasks:

Construct a project schedule to determine the overall cost of and time for the project.

Identify the finish date.

Calculate the total cost.

scribe the process that was followed to review and approve the change request.

Identify the new finish date after the approval of changes.

Calculate the new total cost after the approval of changes.

Use the following information for arriving at your answers:

Task #

Description

Duration

Predecessor

1

Gather requirements

10 days

 

2

Write use cases

5 days

1

3

Get client approval

2 days

2

4

Write specifications

5 days

3

5

Create high-level design

5 days

4

6

Create detailed design and schedule

5 days

5

7

Create user interface

15 days

6

8

Get client feedback

1 day

7

9

Create database

5 days

6

10

Write support modules

30 days

6

11

Unit test support modules

5 days

10

12

Write high-level functions

45 days

6

13

Unit test high-level functions

10 days

12

14

Integration testing

5 days

13,11

15

Acceptance testing

5 days

14,8

Required resources are as follows:

Tasks

Required resources

Gather requirements

Product manager and project manager

Write use cases

Project manager and product manager

Get client approval

Product manager

Write specifications

Project manager

Create a high-level design

System architect

Create a detailed design and schedule

System architect and project manager

Create a user interface

User interface programmer

Get client feedback

Project manager and user interface programmer

Create a database

Database programmer

Write support modules

Coder

Perform a unit test of support modules

Coder

Write high-level functions

Programmer

Perform a unit test of high-level functions

Programmer

Perform integration testing

System architect, programmer, and coder

Perform acceptance testing

Project manager and system architect

Resource hourly rates (in €/hour) are:

Resource

Hourly Rate

Project manager

45.00

Product manager

40.00

System architect

40.00

User interface programmer

35.00

Database programmer

30.00

Programmer

30.00

Coder

25.00

The start date for the project is 12 October. All Saturdays and Sundays are non-working days. Calculate the Saturdays and Sundays on the basis of the current calendar year. Additionally, the following are non-working days:

• 30 November
• 25 December
• 28 December
• 1 January
• 4 January
• 17 March
• 2 April
• 5 April
• 3 May
• 31 May
• 12 July

At the close of the client feedback session (task 8), the head of the sales department wants some changes to be made, and as such, makes a formal change request that day. It takes 14 working days for the change request to be approved.

An analysis of the impact of the change reveals the following:

• Changes to the database module will require 5 days.
• Testing of the new database module will take 5 days following the changes.
• Changes to the support modules will require 7 additional days of work.
• Changes to the high-level functions will require 10 additional days of work.

Reference no: EM13903324

Questions Cloud

Awareness of cultural differences and other problems : As the medical assistant begins an encounter with a patient, awareness of cultural differences and other problems that may inhibit communication is important. Any number of situations may arise that the medical assistant must be prepared to addres..
How corporate social responsibility is moving from optional : Think about what the author is discussing in this article and apply it to the Middle East region and Saudi Arabia, specifically. Do you agree that corporations should play a prominent role in pursuing economic and social justice in the world, or i..
Why do you think this is the case : Transatlantic air travel in business class has an estimated elasticity of demand of 0.40 less than transatlantic air travel in economy class, with an estimated price elasticity of 0.62. Why do you think this is the case?
Identifying an ethical problem : Phase One: Identifying an Ethical Problem- Using the format from the Ethicist column in The New York Times (and discussed in the first week's Professional Practices), identify two ethical problems and write them out, remaining neutral in presentin..
Determine the overall cost of and time for the project : Construct a project schedule to determine the overall cost of and time for the project. Identify the finish date. Calculate the total cost. scribe the process that was followed to review and approve the change request
What is the cost of obtaining financing with sale-leaseback : How much would the corporation receive from a sale-leaseback of the property? What is the cost of obtaining financing with a sale-leaseback? What is the return from continuing to own the property
What is present operating profit per month of kids education : What is the present operating profit per month of the Kids Education Center before Ms. Mooring's salary? What is (are) the break-even point(s), before Ms. Mooring's salary, assuming a student- teacher ratio of 6:1?
Write report to the dean that evaluates quality of analysis : Write a report to the dean that evaluates the quality of this analysis. In particular, focus on concerns about the accuracy of the data and the limitations of cost-volume-profit analysis.
A child pulls a wagon at a constant velocity : A child pulls a wagon at a constant velocity along a levelsidewalk the child does this by applying a 22 newton force to the wagon handle which is incline at 35 degrees to the sidewalk

Reviews

Write a Review

Project Management Questions & Answers

  Explain the steps in the statistical analysis

Explain the steps in the statistical analysis and explain the steps in the statistical analysis

  Show the warned value management

Earned Value Management - Purpose a five minute presentation of the issue, the sides of the argument and your recommendation

  What are some ways to build relationships within the core

When should relationship building between the project manager/other core team members and important stakeholders occur?What are some ways to build relationships within the core team?

  A flow chart as part of a six-sigma quality improvement

A flow chart as part of a six-sigma quality improvement process might be found in which DMAIC category

  Describe in detail your role in influencing groups

Describe in detail your role in influencing groups and individuals throughout your organisation / department. Include all aspects that you feel are important to building positive role modelling and effective communication and consultation processe..

  Computing total cost incurred

What will be the total cost incurred next year?

  Purpose of the project management

Summarize the purpose of the Project Management Institute and provide your thoughts on the PMI methodology and the five phases of the project.

  Different internet access technologies

What are the different Internet access technologies you can use to connect to the Internet?

  Show the construction project planning and control

Show the benefits to the project lifecycle by commencing the planning proccess at the concept and design stages of a construction project.

  What were major duties during the entire project

What criteria would you say you are utilizing to locate your next employment. I have an outstanding performance record of all my undertakings. Therefore, I need not do much; my record speaks for itself. I only post m availability on social platfor..

  Role of leadership and motivation in project management

Critically discuss the role of leadership and motivation in project management utilising appropriate theoretical models to identify how project staff can be led and motivated.

  Risk managers in the healthcare industry

Explain what are some of the skills required by risk managers in the healthcare industry needed to conduct a fault tree and event analysis

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd