Please provide an illustrated project network (a) for the attached and answer (b) ES, EF, LS, LF and slack time (b)
Activity Immediate Predecessors Time (weeks)
A 4
B 6
C A 3
D A 4
E B,C 8
F C 7
G D,E 2
H F 1
Determine the ES, EF, LS, LF, and slack time for each activity.
Create a spreadsheet model for Jesse to calculate profit for sales of the backpacks (one model.) Demand and production quantity for each of the three models are uncertain variables.
What are some of the typical risk variables of your project? Discuss any additional risks that are most likely to occur in your project? How will you mitigate these risks?
What is the forecasted cost at completion (FAC)?- What is the budgeted cost for the work remaining?
The concentration of particulate matter (in parts per million) during a 24-hour period is given.- Find the average concentration during the period from t = 0 to t = 24.
Evaluate the earliest start, earliest finish, latest start, latest finish, and slack for each activity and what are the critical path and duration of the project?
Which shop-floor scheduling rule would you prefer to apply if you were the leader of the only team of experts charged with defusing several time bombs scattered throughout your building?
Using SAS Enterprise Miner or other relevant data mining software, run a neural net model on the Spending and Bankruptcy Data Set to identity the types or characteristics of people who likely file for bankruptcy.
describe a project in which you are currently involved.explain a project in which you are currently involved e.g.
What is a perpetual preferred stock and how is it valued?- How are nonperpetual preferred stocks valued?- What are three potential methods for valuing common stocks, and when does each apply?
Describe the distribution of income and wealth in the United States. Describe the division of the world into high-, middle-, and low-income countries.
You, as the PM, are the project focal point and must set the ethical example for the rest of the project stakeholders and especially your project team.
Can you think of a project for which it might be easier to project real cash flows than to project nominal cash flows?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd