Determine the critical path for this project

Assignment Help Project Management
Reference no: EM131662343

Assignment: Project Planning Developing the Project Plan and Determining Critical Path

1. Using the District4WarehouseMove WBS.xls provided, create a project plan for the District 4 Warehouse Move project. Use the PDF document, Project Plan Check - District4Move, to check your work to be sure you have created your starting project plan correctly. ProjectLibre is required for this task. If you have not yet downloaded ProjectLibre, please click here and follow the directions to do so now.

Note: you will need to insert a column to include your WBS codes, then you will need to sequence the tasks to show tasks by work package.

2. Based upon the details in the WBS and the project case, determine which tasks need to be completed first and which tasks are dependent upon other tasks to be completed prior to starting. Using this information identify predecessors in your project plan's predecessor column. Complete the predecessor column by entering the line number of tasks that must be completed in order for each task to start. This will create your project timeline.

3. Using ProjectLibre's Network or flow diagram view, determine the critical path for this project In a MS Word document, list the activities that are on the critical path. Considering the risks identified in the risk table below, identify which risks would be most likely to increase your project timeline. Justify your responses.

4. Submit both your completed project plan and your MS Word document.

District 4 production Warehouse Move project - Risk Table

1

Permits are not received per the schedule

2

Finish work contractors walk off the job half way through

3

Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled

4

Work benches are poor quality and 1/3 will have to be rebuilt

Assignment Files -

https://www.dropbox.com/s/49ghmarp62abozp/Assignment%20Files%20-%20Project%20Management.rar?dl=0

Reference no: EM131662343

Questions Cloud

What percent was that of the total store : What percent was that of the total store if store sales were $12,980,000?
What patient when counseling her about contraception methods : What questions and/or discussions would be important for the OBGYN to ask the patient when counseling her about contraception methods
What is the maximum penalty that could be imposed on chase : Suppose that a court determined that Chase had aided Regal in willfully understating its tax liability. What is the maximum penalty that could be imposed?
Shopworn and needed a further reduction : At a later date, the remaining pieces became shopworn and needed a further reduction. The buyer reduced them to $19.99 and an additional 15 were sold.
Determine the critical path for this project : Project Planning Developing the Project Plan and Determining Critical Path. Using ProjectLibre's Network or flow diagram view, determine the critical path
Describe and evaluate the reasons why zara success : Describe and evaluate the reasons why Zara success in American market - analyse and evaluate the strategy of the company - Zara Centralized warehouse
Pairs of sunglasses for a special sale : A buyer plans to purchase 250 pairs of sunglasses for a special sale. The sunglasses will retail for $75 each.
Eliminate abuse of power and corruption : What can be done to prevent or eliminate abuse of power and corruption?
Find the cost of one hot dog and the cost of one hamburger : At a concession? stand, five hot dogs and fourhamburgers cost ?$12.25 fourhot dogs and fivehamburgers cost ?$12.50 Find the cost of one hot dog and the cost.

Reviews

len1662343

9/28/2017 4:55:03 AM

Topic: Project Management. Detailed Question: Please see my attached assignment, I need for you to provide references after each chapter and statement and a reference page. I will put them in format order. http://www.projectlibre.com/ is where you can go to download the ProjectLibre. Note: you will need to insert a column to include your WBS codes, then you will need to sequence the tasks to show tasks by work package. Submit both your completed project plan and your MS Word document.

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd