Determine about the project schedule

Assignment Help Project Management
Reference no: EM132542937

Problem 1

Part (b) of this Problem refers to the network diagram below.

963_figure.jpg

a) The project manager can use a network diagram like the one above to carry out a forward pass and backward pass to calculate, among other things, the ES/EF and LS/LFtimes for each of the activities in the project.

i. What additional information will the project manager be able to determine about the project schedule after performing these calculations? Why is this information important to the project manager?

ii. What else does the project manager need to know to complete the project schedule andhow might this additional information impact on the results from part (i)? Explain.

b) This Problem refers to the network diagram at the start of this question.
i. Youare required to shorten the duration of the project in the network diagram above by 1 week less than its earliest finish time. Only the activities in the following table can be shortened (crashed). They can all be crashed by up to 2 weeks. The costs to crash each activity are shown in the table below. Activity I cannot be crashed. What activity (or activities) would you crash if you are required to shorten the project duration by one week for the lowest possible cost. You must explain your choice(s).

Activity

Cost to shorten task by 1 week

A

$3000

B

$1500

C

$1000

D

$1000

E

$800

F

$1000

G

$900

H

$4000

ii. In practice it may not be quite as straightforward to crash (shorten the duration of) a project as this exercise suggests. Explain what can complicate this process in practice.

iii. Discuss the risks associated with compressing (or crashing) projects.

Problem 2
The following table shows the currentstatus data for a project at the end of month 3.

PV

(Planned Value)

EV

(Earned Value)

 

AC

(Actual Cost)

 

SV

CV

SPI

CPI

$18,461.54

$35,673.08

$20,673.08

 

 

 

 

If you were the project manager for this project, should you have any concerns about this data?
If yes, then
• what are your concerns?
• what might be some underlying causes?
• how might you combat these in the future?
If no, then explain why not.

Reference no: EM132542937

Questions Cloud

Compute the companys break-even point : Jones Company is starting a business to distribute a single product, an umbrella whose selling price is $16, Compute the Company break-even point
What is the limiting reactant : What is the limiting reactant and how much ammonia is formed when 5.65 g of nitrogen reacts with 1.15 g of hydrogen?
What will the new celsius temperature be : If a balloon at 25* C with 2.3 L of volume is expanded to 40.0 L, what will the new Celsius temperature be?
What is the companys contribution margin : Last month Alpha Company sold 40,000 units, total sales were $300,000, What is the companys contribution margin
Determine about the project schedule : Discuss the risks associated with compressing or crashing projects - What else does the project manager need toknow to completethe project schedule
Describe relationship between internal and external equity : Discuss the basic building blocks of developing a market competitive pay system, including the relationship between internal and external equity.
Generate the direct labour budget : Generate the direct labour budget (in hours and £'s) for the quarter June to August 2020. Direct labour costs £12 per hour, and each T-shirt takes 0.4 hours
Evaluate the concept of market competitiveness : Evaluate the concept of market competitiveness in relation to an organization's pay system, particularly when it is unable to offer its employees market.
Use of electromagnetic radiation important : Find an article that illustrates why the use of electromagnetic radiation important to a real-life application. And explain the article

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd