Determine about the project schedule

Assignment Help Project Management
Reference no: EM132542937

Problem 1

Part (b) of this Problem refers to the network diagram below.

963_figure.jpg

a) The project manager can use a network diagram like the one above to carry out a forward pass and backward pass to calculate, among other things, the ES/EF and LS/LFtimes for each of the activities in the project.

i. What additional information will the project manager be able to determine about the project schedule after performing these calculations? Why is this information important to the project manager?

ii. What else does the project manager need to know to complete the project schedule andhow might this additional information impact on the results from part (i)? Explain.

b) This Problem refers to the network diagram at the start of this question.
i. Youare required to shorten the duration of the project in the network diagram above by 1 week less than its earliest finish time. Only the activities in the following table can be shortened (crashed). They can all be crashed by up to 2 weeks. The costs to crash each activity are shown in the table below. Activity I cannot be crashed. What activity (or activities) would you crash if you are required to shorten the project duration by one week for the lowest possible cost. You must explain your choice(s).

Activity

Cost to shorten task by 1 week

A

$3000

B

$1500

C

$1000

D

$1000

E

$800

F

$1000

G

$900

H

$4000

ii. In practice it may not be quite as straightforward to crash (shorten the duration of) a project as this exercise suggests. Explain what can complicate this process in practice.

iii. Discuss the risks associated with compressing (or crashing) projects.

Problem 2
The following table shows the currentstatus data for a project at the end of month 3.

PV

(Planned Value)

EV

(Earned Value)

 

AC

(Actual Cost)

 

SV

CV

SPI

CPI

$18,461.54

$35,673.08

$20,673.08

 

 

 

 

If you were the project manager for this project, should you have any concerns about this data?
If yes, then
• what are your concerns?
• what might be some underlying causes?
• how might you combat these in the future?
If no, then explain why not.

Reference no: EM132542937

Questions Cloud

Compute the companys break-even point : Jones Company is starting a business to distribute a single product, an umbrella whose selling price is $16, Compute the Company break-even point
What is the limiting reactant : What is the limiting reactant and how much ammonia is formed when 5.65 g of nitrogen reacts with 1.15 g of hydrogen?
What will the new celsius temperature be : If a balloon at 25* C with 2.3 L of volume is expanded to 40.0 L, what will the new Celsius temperature be?
What is the companys contribution margin : Last month Alpha Company sold 40,000 units, total sales were $300,000, What is the companys contribution margin
Determine about the project schedule : Discuss the risks associated with compressing or crashing projects - What else does the project manager need toknow to completethe project schedule
Describe relationship between internal and external equity : Discuss the basic building blocks of developing a market competitive pay system, including the relationship between internal and external equity.
Generate the direct labour budget : Generate the direct labour budget (in hours and £'s) for the quarter June to August 2020. Direct labour costs £12 per hour, and each T-shirt takes 0.4 hours
Evaluate the concept of market competitiveness : Evaluate the concept of market competitiveness in relation to an organization's pay system, particularly when it is unable to offer its employees market.
Use of electromagnetic radiation important : Find an article that illustrates why the use of electromagnetic radiation important to a real-life application. And explain the article

Reviews

Write a Review

Project Management Questions & Answers

  Techniques to speed up a project

What are some techniques to speed up a project? Under what circumstances might they be implemented? Is hiring/adding more staff always a boost to timely project schedule completion?

  Determine risks facing a project

Select a Risk Identification Method and Use it to Determine Risks Facing a Project

  The total cost in completing the project in normal time

S M Construction has been awarded a contract to build a new manufacturing plant just outside Cardiff. The activity on arrow table below gives data on the activities involved in the plant’s construction.

  Concept of change management process in a projectexplain

concept of change management process in a projectexplain the concept of the change management process within a

  Procurement in the project management process

Analyze the importance of procurement in the project management process.

  Explain the change theories of lewin change model

Explain the change theories of Lewin's Change Model - by Kurt Lewin (unfreezing, Change/Moving and refreezing) and describe the processes.

  Duration estimation techniques in project management

In a short response, describe the advantages and disadvantages for each of the five techniques. Include an example of when it is appropriate to use each technique.

  Computer breakeven cash inflows for etsitty arts incs new

computer breakeven cash inflows for etsitty arts incs new projectetsitty arts inc. a leading producer of fine cast

  Monitoring and controlling project cost

Earned Value Analysis - Monitoring and Controlling Project Cost - What are some key components to monitor the health of the project, as it relates to earned value?

  Determine your best course of action for bringing project

Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution.

  Review the warehousing aims

Identify at least two aims that you have seen implemented at your current organization. In 200-250 words, explain why that aim was implemented.

  How will project communications

How will project communications and interactions work between the project manager, the stakeholders and the project team

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd