Company Background

Tan Hui Hui is a newly appointed Director of IT in one of the largest pharmaceutical companies in Singapore. The company provides a comprehensive pharmaceutical care services to a large number of Singapore's residents. Some of the services include Hypertension-Diabetes-Lipidemia clinic, Smoking Cessation clinics and consultancy services for treatment of minor ailments, travel or nutritional advice. The company also provides an online shopping portal where their customers can order their medications and have them delivered to their home via the company's home delivery service.

The company relies heavily on IT to achieve the company's mission to improve the health and well-being of their customers through a high-quality patient-centric healthcare approach that emphasize on accessible, effort-free and cost-effective services. One month into her job, she realized there were some challenges in the way how IT projects were being selected and managed in her company.

First, she noticed that there were a large number of IT projects that were on-going across her department. Many of her staff constantly complained to her that the resources in the department were simply insufficient to cope with the demands from managing such large numbers of IT projects implementing concurrently.

Second, staff in her department was often involved in multiple projects at any one time. They frequently complained about how inefficient and political their project meetings had become. People often fought over the best way to implement a project. As a result of the talent crunches, project managers in the department were also found competing fiercely for the best to be involved in their own projects.

Third, senior management often did not provide a clear strategic priority on many of the IT projects in her company. This has resulted in some of her department's project managers deciding to make their own choices on which projects that they should prioritize to work on. The consequences are severe as some of the projects are left to their demise over time. Finally, the constant infighting among project managers has led to a low morale and mistrusting environment across her department that consists of around 200 staff.

Together, these factors have led to many of the IT projects not being able to meet its project's schedule and budget. The Chief Operating Officer fired the previous Director of IT exactly because of these factors and hired Hui Hui specially to resolve these challenges in the company.

As Hui Hui takes stock of the current situation in her company, she knows that a project portfolio management system will be one of the solutions that she should consider.

Hui Hui compiled all the recommendations provided by your team into a presentation for the management.

While doing so, she realized that she would need to estimate the amount of resources (e.g. manpower and finances) that she would need for her project portfolio management project.

She worked closely with your team to come up with the following task responsibility matrix and the type of expertise that she would need for each task.

Activity

1

2

3

4

5

6

Table 1: Project's tasks information

DescriptionDurationPredecessor

(Man-days)

Project Portfolio Management Project

Assemble project team10 days

Develop project priority scheme5 days2

Develop project screening process10 days2,3

Develop project schedule5 days2

Compile project system requirements18 days5,3,4

Resource

7

8

9

Compute project costing

Seek senior management approval

Purchase system

5 days

2 days

15 days

3,4,6

7

8

Project Manager

Project Manager

Project Manager

Project Manager

Senior System

Analyst, Senior

System

Administrator,

Project Manager

Project Manager

Project Manager

Senior System

Analyst, Senior

System

Administrator,

Software: One-

time investment

S$25,000/=

Hardware: One-

time investment,

S$100,000.

Senior System

Administrator

System Analyst

A, System

Analyst B, Senior

System Analyst,

Senior System

Administrator

Project Manager,

Senior System

Administrator,

Senior System

Analyst, System

Analyst A,

System Analyst B

Project Manager

Senior System

Administrator,

Senior System

Analyst, System

Analyst A,

System Analyst B

Page 7 of 10

10

11

Install system

Develop & configure system

18 days

12 days

8,9

8,9,10

12

Perform system test

10 days

10

13

14

Communicate to key stakeholders

Prepare system for go live

8 days

18 days

8,12

12

Activity

15

Go live

Description

Duration

(Man-days)

20 days

Predecessor

13,14

Resource

Project Manager,

Senior System

Administrator,

Senior System

Analyst, Business

Analyst A,

Business Analyst

B, Business

Analyst C,

Business Analyst

D

Project Manager,

Senior System

Administrator,

Senior System

Analyst

16

Document project for closure

4 days

15

The unit cost for each of the resources is shown in the table below. Assume each working day

starts at 8 am and ends at 5 pm and includes lunch time of 1 hour (12 pm to 1 pm).

Title

Project Manager

Senior System Analyst

Senior System Administrator

System Analyst

Business Analyst

Software Cost

Hardware Cost

Cost

S$50/hr

S$30/hr

S$30/hr

S$20/hr

S$20/hr

S$25,000

S$100,000

Overtime Cost

S$80/hr

S$50/hr

S$50/hr

S$30/hr

S$30/hr

N.A.

N.A.

Question 1

Using the information above, demonstrate your understanding on project management by the estimated total cost for the project and the corresponding costs of each task in MS project. You must arrange the appropriate tools in MS Projects to answer the question.

Present your answer using screen captured from MS Project. Answer not using MS project will get zero mark.

Question 2

After allocating the resources into each of the task, Hui Hui realized that there were some resource allocation issues in the project.

(a) Using MS Project, identify and analyse all the tasks that have resource overallocation issues. Present your answer using a screen capture of the MS Project information.

(b) For each of identified resource overallocation issue, examine and appraise what would be your strategy to address each one of them.

ECA - January Semester 2015

(c) For each of your strategy, analyse and discuss what would be the impact, in terms of cost, quality, scope or risk, of your strategies to the project.

Hui Hui subsequently realized that she had made a mistake in the configuration of the dependencies of task 12. Task 12 is dependent upon task 11 but is not being set so. She had also decided to perform resource levelling on all the remaining tasks to address the identified
resource overallocation issues.

Question 3

Update your MS Project schedule accordingly and present the screen shots of the Gantt Chart and the project costs. In addition, evaluate the information in MS project, and answer the following questions.

(a) What is the new project end date?

(b) What is the new project duration?

(c) What is the new estimated project cost?

(d) What is the critical path of the project?

Question 4

Identify & critique the project schedule and cost estimation technique that Hui Hui has employed in question 1, 2 and 3 (Taking into consideration information presented in this You may briefly propose an alternative.

Reference no: EM13839583

Questions Cloud

Develop a detailed npv model in excel showing cash inflows : Develop a detailed NPV model in excel showing Cash Inflows, Cash Outflows and NPV of the project. What is the amount that you either expect to receive or are willing to pay the State Government to win this concession.
Two angles whose sides are opposite rays are called _angle : Two angles whose sides are opposite rays are called _____ angles
Draw the production possibilities frontier : Draw the production possibilities frontier based on the data in the above table. What is the opportunity cost of one pound of butter? How can you tell?
What is an advantage to using abab over aba or ab designs : Give an example of an ABAB single-subject design. What is an advantage to using ABAB over ABA or AB designs?
Demonstrate your understanding on project management : Demonstrate your understanding on project management by estimated total cost for project and corresponding costs of each task in MS project. You must arrange appropriate tools in MS Projects to answer question.
What is the difference between a nonequivalent control group : What is the difference between a nonequivalent control group design and a pretest posttest control group design?
Issues in psychology article - addiction : For this assignment you will complete a summary review of an scholarly, peer-reviewed journal article on an important issue in psychology selected from the list below. Issues in Psychology Article Summary Topics- Addiction, ADHD and Aging
Rank these designs in order of level of internal validity : Rank these designs in order of level of internal validity, from lowest to highest: pre-experimental design true experimental design quasi-experimental design
Analyze the variance for the budgeted amount : Calculate and analyze the variance for the budgeted amount and the actual amount spent. Along with each variance calculation, prepare a brief justification of why there may be a variance.

Reviews

Write a Review

Project Management Questions & Answers

  1 select two brands within your product category with very

1. select two brands within your product category with very different marketingpromotion strategies. submit as exhibits

  Purpose of analyzing the risk of a decision

Purpose of analyzing the risk of a decision - Explain what is the purpose of analyzing the risk of a decision

  Salary administrationbased on glenviewillustrate the wage

salary administrationbased on glenviewillustrate the wage and salary administration process explain how compensation is

  Explaining member of a manager-managed llc

Eric is a member of a manager-managed LLC but is not a manager. This LLC invests in real estate and manages it as rental property in a college town.

  Explain what are organizational strengths and weaknesses

Explain what are the organizational strengths and weaknesses and how can management increase its understanding and application of business etiquette and protocol in this new region?

  Perform a stakeholder analysis for the researched project

Perform a stakeholder analysis for the researched project in which you: Include all major stakeholders that the project will require. Describe each stakeholder's title, role within the project, and objectives each should meet for the project

  Show the project proposal outline and summary

List the desired outputs from the project. Specify the performance criteria for the project and a statement of work (SOW) must be developed to define what is and what is not included in the project.

  New information systems are built as solutions to problems

new information systems are built as solutions to problems or means for improvement.your task is to use laudon amp

  Calculate potential financial implication

Develop a plan to calculate potential financial implications for a nationwide company of your choice. Provide a scenario in which a break-even sales analysis for reactive pricing would be the best option for a company.

  What is the objective function

Let x1 be the number of units to make and x2 be the number of units to buy. If it costs $1.5 to make a unit and $4 to buy a unit and 4,000 units are needed, what is the objective function?

  The franchisor of hotels to improve their relationship

What suggestion would you recommend to the franchisor of Hotels to improve their relationship with franchisees?

  Apply the compensation knowledge in real-world situation

To apply the Compensation knowledge in real-world situation and identify the existing problems at Zenith Medical System and analyze the underlying organizational factors that are causing those problems.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd