Define your organisation and project

Assignment Help Project Management
Reference no: EM13837519

Advanced Engineering Project Management

Assignment

Special Instructions

1. Answer all questions, and ensure that your answers have the coverage, and are in the format, requested.

2. Present your own ideas.

3. Your answers should be properly referenced and reflect that you have undertaken research outside the study material. You are to use the Harvard AGPS referencing system, information which is available from the USQ Library webpage:

https://www.usq.edu.au/library/referencing/harvard-agps-referencing-guide

4. You will require a table of contents for your answer to Part A.

5. You will require an abstract and table of contents for your answer to Part B.

6. You should include a word count for each of Part A and Part B of Question 1. Word counts exclude the List of References.

7. It is expected that your written answers will be produced using electronic word processing. The ‘.pdf' format is preferred for written answers.

8. Calculations for the project budget should be clearly explained.

9. Assignments will be submitted electronically via the Study Desk.

10. There must be a turnitin result for your answer. Otherwise it will not be accepted. turnitin is the plagiarism detection service used by USQ to examine student submissions as they are uploaded to the study desk. If the system does not successfully generate a turnitin result, students should try a different file format or contact the course examiner.

11. Please note that if plagiarism or cheating is detected in this assignment it will result in no marks for the assignment. Students should ensure they clearly understand the meaning of plagiarism and cheating. In particular, students should understand that while they may collaborate with other students on the conceptual ideas in their assignments, the final written report submitted by each student must be unique, and must not contain the written material of (a) any other student in the course, or (b) by any other person without due acknowledgement.

Question 1:

Developing a Revised Project Management Plan and Report to Management

Background

You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:

• Consultant

• Government organisation

• Construction company

• Installation company

• Asset management provider

• Maintenance services provider

• Other.

The organisation may be operating in one or more engineering disciplines, such as civil, mechanical, electrical, environmental, mechatronic, biomedical, or other discipline, or in construction or surveying.

Your organisation has asked you to review the management of a medium sized project (up to $5 million in value), which is to be completed within two years of its commencement. The project has at least 20 main activities and at least two (2) critical paths.

The project commenced eight months ago. The first six weeks were spent developing the project charter and preparing the original project management plan. Project execution (carrying out the work) commenced immediately the project management plan was completed and approved.

There will be a one (1) month project closing period at the end of the project. During this time, equipment will be tested and commissioned (if relevant to your project), and the project will be finalised.

The project deadline is firm, subject to any justifiable contingencies.

The existing business case and project charter are not detailed. Similarly, the project management plan, including a basic Gantt chart and high level budget is not well detailed or described.

There are a number of issues with the project:

1. To date, the project is two (2) months behind schedule. Part of this delay has resulted from poor understanding of lead times for delivery of particular project components. There are no other significant factors that should impact on project delivery.

2. Because there is only a quite basic project plan and time schedule, there is poor sequencing of critical activities. They do not have clear scheduled completion dates.

3. There have been delays in procuring some critical project resources. There may be alternative suppliers.

4. While there were a number of specialised personnel for particular aspects of the project available at the start of the project, they were not booked ahead of when they were required. Most of these resources are now booked for several months ahead. Few alternatives are available.

5. As a result of the influence of a number of stakeholders, there has been significant scope creep, which with the current rate of progress will delay delivery by one (1) month. This scope creep also threatens to impact on the project's business case.

6. Some components of the project have not been delivered or built to the required quality specification. Consequently, there have been delays while defects have been rectified.

7. Communication between project manager, project sponsor, stakeholders, contractors, consultants and other key personnel has not been good. There are therefore a number of cases where key information has not been communicated well. This poor communication has impacted on project progress.

You have been charged with delivering a revised project management plan to deliver the project on time; and with providing a report to the Project Sponsor explaining the actions you have taken.

Your Task

Part A (maximum 3000 words)

1. Define your organisation and project.

Nominate an organisation of your choice, and the engineering discipline or disciplines in which it is operating.

Nominate a suitable project (for example, road development, subdivisional development, power station, mobile phone network, mining,

provision of industrial equipment, installation, maintenance, surveying) to use as an example.

2. Prepare a revised project charter, including an updated business plan.

3. Prepare an updated project management plan for completing the project within its original timeline.

The project management plan should include the following:

• Definition, preparation and definition of subsidiary plans

• Identification and description of stakeholder needs

• Work Breakdown Structure (WBS)

• Plans for the project management Knowledge Areas of:

• project integration management

• project scope management

• project time management

• project cost management

• project quality management

• project human resource management

• project communications management

• project procurement management

• Definition and sequencing of the main project activities

• Main activity resources and durations

• Project schedule, costs and budget

Notes:

• The project charter should include a revised business case for the project and link the project with your organisation's strategic plan. On the basis of this business case, the project sponsor will make a decision about the future of the project.

• You may assume that the project sponsor has allowed the project timeline to be increased by one (1) month to allow for the scope creep already approved. However, further scope creep is not permitted.

• The project scope management plan should include a section on controlling scope creep

• The project time management plan should include a Gantt chart showing the major project activities.

• The project cost management plan should include all costs reasonably expected to be incurred in delivering the project. These costs may include estimates for ensuring completion of the project.

4. Prepare a plan for executing, monitoring and controlling the project.

5. Prepare a plan for any testing and commissioning, and for closing the project

Part B (maximum 1000 words)

Write a report to your Project Sponsor that:

• succinctly outlines the steps you have taken to deliver the project within its original timeframe
(as extended by permitted scope creep of one (1) month)

• explains why they have been taken

• demonstrates how they will enable the project to be completed within its original timeframe

• discusses the additional costs that will be incurred to achieve this target

Part C (Written Communication)

Abstract and table of contents

Structure

Language, style, spelling

Completion in within word count

Setting out and referencing.

Reference no: EM13837519

Questions Cloud

Discuss how a project''s risk can be incorporated : In 250 words, discuss how a project's risk can be incorporated into capital budgeting analysis. Should discounted cash flows be used to evaluate capital budgeting projects?
Locate and cite relevant quantitative evidence to support : Locate and cite relevant quantitative evidence to support assertions. Demonstrate appropriate communication strategy for a specific audience
Why would your company want to reduce : Why would your company want to reduce its accounts payable policy? A. Reducing their payables will increase their available cash B. Reducing their payables will slightly increase demand
Define capital budgeting in finance : 1. How do we traditionally define capital budgeting in finance? 2. What is the purpose of capital budgeting in a business firm and how is it used?
Define your organisation and project : Define your organisation and project. Nominate an organisation of your choice, and the engineering discipline or disciplines in which it is operating.
How can jobs be created after students graduate from college : How can jobs be created after students graduate from college, and when and how do you suggest they begin paying their student loans back and for how long
Difference between technical and business requirements : Explain the difference between technical and business requirements What are the pros and cons of building vs buying segments of the system?
What is your effective borrowing rate : Compute the break-even IBM stock price for each option and compute the price of the call - What is your effective borrowing rate?
Propose a solution to prevent the environmental problems : Propose a solution to prevent the environmental problems of the seaport of troy described in the ecofact

Reviews

Write a Review

Project Management Questions & Answers

  Quantitative analysisnetworks pert critical path

quantitative analysisnetworks pert critical path. helpcompany x has been told to install some new equipment. the

  Structure and document plan in form of a top-down flowchart

Create a plan that will take you through the steps and tasks associated with understanding, researching, developing, writing, refining and producing all the other parts of this assignment. Structure and document the plan in the form of a top-down f..

  What is involved in production of articles

The scope statement should include a full description of the project requirements, including the project aims, objectives and key milestones This chart should clearly identify how the project is to be broken down into manageable tasks. This includes ..

  Accomplished in the ribbon on the task tab and tasks group

Directions For CP3 you will set your CP2 project and document deliverable aside and start fresh. Your task is to use this document and the data provided to create a project file using Microsoft Project. The data below will establish a project budget ..

  Degree of precedence relationship among the activities

Prepare a project network consisting of at least 20 steps that should be done to complete the project. Be sure to indicate some degree of precedence relationship among the activities.

  Project selection - annual earnings approximate cash flows

Suppose only one project can be chosen and the annual earnings approximate cash flows excluding finance charges, which project should be chosen?

  Explain about conflict management and communication

Provide an example requiring conflict management and show how the incident was handled, what the results were, and what might have been done to improve the situation.

  Description of project analysisthe guo chemical corporation

description of project analysisthe guo chemical corporation is considering the purchase of a chemical analysis machine.

  Design the authorities of a project manager at bec

What caused the conflict between the project managers and the other employees and how would you design the authorities of a project manager at BEC?

  Gun manufacturer liability case

Prepare an expert engineer argument for the court on why or why not the gun's manufacturer should be held responsible for a "defectively designed product." Limit to one-half page.

  Project managemet work break down structureyour next step

project managemet work break down structureyour next step in the project management process is to create a work

  Write paper on inventory management systemreport

write paper on inventory management system.report containsabstractacknowledgementintroductionmotivation for the project

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd