Define the term integration management

Assignment Help Project Management
Reference no: EM13529205

1. Liquidation value of the firm's assets could be considered as________________

a. The minimum wealth of shareholder
b. The maximum wealth of shareholder
c. The average wealth of shareholder
d. None

2. If ‘P' be the initial investment, ‘I' be the interest rate and ‘T' be the time period for which funds are invested then interest earned will be______________

a. P*I/T
b. P*T/I

c. (P*I*T)2

d. P*I*T

3. Following the above given conditions, compound Interest be given by___________

a. P*(1+I)1/T
b. P*(1+I)T
c. (P*I*T)T
d. Can not be calculated

4. Firms resorting to ‘Proactive Growth'?
a. Do constant strategic planning
b. Watch things happening
c. Never plan but work on fortune
d. None

5. ‘SPACE' stands for___________________

6. Increasing marketing expenditure leading to an increased market share is known as________________
a. Market development
b. Market penetration
c. Market expansion
d. Market growth

7. If profit after tax is ‘A' ,depreciation be ‘B' and interest be ‘I' then Interest cover ratio is given by______________

8. E-V rule is also called_____________
a. Mean co variance rule
b. Mean variance rule
c. Mean deviation rule
d. None

9. In case of internally generated funds the opportunity cost to the firm is____________
a. Zero
b. The lending rate
c. The borrowing rate
d. None
10. ‘PERT' stands for__________________

Part Two:

1. Write a note on ‘Sinking Fund Payment'.

2. Differentiate between PERT and CPM Model?

3. What is ‘Capital Asset Pricing Model (CAPM)'?

4. What do you understand by PBP (Payback Period Method)?

5. Briefly explain the planning for procurement? 

Project partnering at British Airports Authority (BAA)

The construction sector in recent times has not been noted for its high levels of performance. Firms like BAA, who own and operate airports including Heathrow and Gatwick - London's two major airports - rely heavily on their suppliers, including their construction suppliers, for their own performance. Where construction projects are delayed, the financial consequences can be disastrous. Furthermore, the disciplines of working on airport premises, including the security issues, play a significant part in the daily working lives of project staff. New firms bringing new staff onto the airport sites invariably require time to bring them up to speed with the appropriate ways of working.
Particular problems include:

- Security - all personnel with access to airside parts of the airport (i.e. past passport control) must be security vetted and trained. The vetting process takes six weeks, so firms must prepare project staff in advance;

- Deliveries - getting materials into the airport is problematic, due to significant congestion and lack of availability of areas for storage;

- Constant use of terminal buildings by passengers - the closing of areas causes problems with passenger capacity. The firms are required to work with the constraints of passengers using the areas around where the work is being carried out and physical and noise intrusion must be kept to a minimum;

- The commercial activities (shops and restaurants) are the economic lifeblood of the business, with large ground-rents. The objective of projects involving these areas is not simply to complete works on time but as early as possible, so that the areas can start to generate rental incomes.

The traditional approach to managing fit-out projects (changing internal layouts to accommodate different facilities and in particular new retail facilities) was that every contract was different, and would be negotiated with different contractors. These would then employ their own sub-contractors to carry out parts of the work. The approach that has worked far better for all concerned has been through the appointment of lead contractors, with long-term contracts - in most cases 10 years - to be the prime supplier of fit-out services to B.A.A. This particular contract was awarded to MACE. As part of the agreement, BAA has paid for MACE staff to attend training programmes. This has extended further, with help being offered to their suppliers - of both materials and labour - for development. Where particular problems are identified, the supplier can be asked to take part in an improvement programme. Satisfactory completion can result in similar long-term deals (tied to continual improvement) being offered to those suppliers. In some cases the problems - particularly with designs for areas - have been the responsibility of BAA. The mechanisms are now in place to identify these problems and to introduce new practices to avoid them in future.

1) Summarise the arguments for such a policy of partnering with a major supplier such as BAA and MACE have done here.

2) Carry out further research to identify further examples of partnering in projects. How well do they appear to be working?

Caselet 2

The Big Dig

Any project that involves tunnelling is risky. Any project that involved tunneling under a city whilst trying to keep that city fully operational, is very risky. When that city is bottom in the USA, it is in a risk category all of its own. This does not, how - ever, excuse the financial performance of this project, the results of which are exceptional and even make the performance of previous ‘stars of disaster' such as the Channel Tunnel, look good. During the 1950s, the Commonwealth of Massachusetts commissioned new roads as part of a national road-building frenzy that took place at that time. The result was a partly elevated freeway that cut the city off from its old harbour and over time coped increasingly less well with the volumes of traffic that were trying to use it. For many years, the project had been the subject of much politicking and had been rejected by a number of national administrations. In 1993, it was given the go-ahead. At this time the budget was $US2.6

billion, an enormous sum of money for an 8-mile tunnel, but given the technical complexity of the task, this was considered acceptable. Gradually the costs rose, until in 1998, the estimated final cost was 410.4 billion. By mid-2000 this had risen to $13 billion and by mid-2001 to over $15 billion. It was still considered a technical success, but both politically and economically, it was a disaster. In project management terms it is also a disaster - a 500 per cent-plus overrun on budget can only be described as ‘talented'. How did such a financial disaster occur? The first is a feature of many large ‘political' projects - that the ‘real cost' would not be politically acceptable. The original budget was deliberately deflated to make the project happen. The second is technical risk - that of the tunnelling process. The ground through which the tunnelling is being carried out is reclaimed land that was originally under the sea. The tunnelling process being used was also new, presenting a degree of technical novelty.

1) How might the project be considered a technical success but an economic, political and project management disaster?

2) Suggest how the 500 per cent-plus overrun might have come about. 

1. Define the term Integration Management? And how would you explain the Project plan in detail?

2. The funds and personnel requirements of the project change significantly with the stage of its life cycle. What are the stages in the life cycle of project? Describe them.

Verified Expert

Reference no: EM13529205

Questions Cloud

Define molar concentration of sodium thiosulphate solution : Deionized water from a wash bottle was added to wash down the wall of the receiving flask during the titration .how does this affect the reported molar concentration of the sodium thiosulphate solution. explain
How far along the surface of the ramp does the block slide : A 150-g block is projected up a ramp with an initial speed of 8.1 m/s. If the ramp is inclined 28° with the horizontal, how far along the surface of the ramp does the block slide before coming to a stop
Find what minimum distance does it take to stop the car : An automobile is going up a grade of 13° at a speed of 27.5 m/s. The coefficient of static friction between the tires and the road is 0.70. What minimum distance does it take to stop the car
Explain the molar concentration of the kio3 solution : How does this technique error affect the molar concentration of the KIO3 solution. Will the reported molar concentration of the standardized Na2S2O3 solution be too high, too low, or unaffected
Define the term integration management : Define the term Integration Management And how would you explain the Project plan in detail -  How might the project be considered a technical success but an economic, political and project management disaster?
Define what is the specific heat of the metal : The thermal equilibrium temperature of the metal sample plus water mixture is 28.3 degree. What is the specific heat of the metal
How to calculate the kc moles of pure so3 : Calculate the Kc moles of pure SO3 (g) are introduced into an 8.00dm3 container at 1105k. At equilibrium,, 0.58 mol of O2(g) has been formed.for the reaction: 2SO3(g) 2SO2(g) + O2(g)
Determine with what speed was the rock thrown : A rock is thrown from the top of a 30 m building at an angle of 47° above the horizontal. If the horizontal range of the throw is equal to the height of the building, with what speed was the rock thrown
Define how many coulombs are required to plate : How many coulombs are required to plate a layer of chromium metal 0.25 mm thick on an auto bumper with a total area of 0.32 m2 from a solution containing CrO42-? The density of chromium metal is 7.20 g/cm2.

Reviews

Write a Review

Project Management Questions & Answers

  Explaining planning a scrupulous effort

Taking a cue from the above, planning is a scrupulous effort that needs to be well documented in order for projects to succeed.

  Prepare a job description for project manager role

Prepare a job description for the project manager role to document for future candidates. In your summary, describe the main responsibilities that must be completed by a project manager.

  Project organization reflects organizational strategies

Discuss if the project organization reflects organizational strategies and discuss if there has been a proper selection of project sponsor and project manager

  Project management and changeyou have been assigned to

project management and changeyou have been assigned to project manage the opening of a new restaurantexplain what kinds

  Differentiating cost account budget and time phased budget

What is the function of a project budget? Explain the difference between a Cost Account Budget and a Time Phased Budget?

  Debtholders and shareholdersscenario project a has a

debtholders and shareholdersscenario project a has a guaranteed a payoff of 200 million which will exactly compensate

  Discuss main factors that influence choice of manufacturing

Example an organization or a product from an industry that you are familiar with, critically discuss the main factors that influence the choice of a manufacturing/service process design.

  Describe how a work breakdown structure can be useful

Describe how a work breakdown structure can be useful during the estimating of a project budget

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Explaining schedule variance and cost performance index

What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

  Show the primary function of a project plan

Show the primary function of a project plan and explain the nine categories of information in a project master plan.

  1 what are the major improvements performance they achieved

1. what are the major improvements performance they achieved in the miami childrensnbsphospital with lean service and

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd