Question 1) Following are cost and schedule data for a project that is underway.
Project Cost Data
Month
Actual
1
12
2
23
3
55
4
5
53
6
60
7
75
8
80
9
10
11
Project Schedule Data
Task
Planned Starting Month
Planned Duration (months)
Actual starting month
Actual Duration (mths)
A
C
3 so far
D
2 so far
E
Not yet begun
F
a) Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs
b) Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance
Verified Expert
In the given assignment, we were required to derive cost table, calculation of cumulative costs and drawing of the cumulative cost curve. Based on the data, we further required to draw Gantt chart comparing the actual schedule with the planned schedule.
Create a formal document to the CEO of the company. Create a disaster recovery plan for the employees and vendors in case of a breach.
Develop a project concept. Find a stakeholder who will act as sponsor for the project. Outline the business problem that the system is intended to address, and establish an initial business case for the system.
What steps do you think a Project Manager should take in order to increase the likelihood that lessons learned from previous projects are used to effectively improve the results of future projects?
PMAN 637 9042 Project Risk Management - Your team MPP has a schedule of upcoming dates for March and April. Add one risk relating to your final Team Project
Distinguish the three types of damages available in tort cases.- List five intentional torts and explain the elements needed to prove each.
Discuss how this department should look first for product problems/ideas. - What types of information might be obtained from this source?
What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index SPI for the project?
Outline and explain contract administration policies and procedures. Examine external influences on the procurement and risk management process.
Obstetrics history and well young adult behavioral health history. Complete the Health History and Screening of an Adolescent or Young Adult Client worksheet.
Using the project you identified in Problem 1, create a Responsibility Assignment Matrix (RAM) for it, identifying at least six fictitious project team members.
The union challenged the Rocky Mount ordinance as unconstitutional. The city defended its ordinance as necessary to protect the safety and welfare of the citizens. Decide.
Why does the return on assets differ between Company A and Company B? Why do companies with equity investments tend to have a lower return on assets than companies with only core operations?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd