Critical path of a pert chart

Assignment Help Project Management
Reference no: EM1338399

Q1) You are the general manager of a large construction project. The contract has both financial incentives for finishing on time or early as well as large penalties if the project is completed late. To get the project done on time or early that project planning using a formal timeline is essential. You ask the project manager to address the following questions:

1. In terms of creating a timeline, what is meant by the critical path of a PERT chart?

2. As a project manager you know that the fastest possible time a project can be completed is known as the critical path. This implies that any delay in any step of a projects critical path, will therefore delay the overall project. On a particular project, step B is part of the critical path; step C and D both are not. Assume that all of these steps, B, C, and D are at risk of being delayed due to some issue (could be lack of people, lack of materials, equipment downtime - it makes no difference).

How would the manager go about prioritizing correction of the problem existing in B, C, or D?
Should the manager address the issue in step B first, step C first, or step D first; why?

3. Once repair is completed in step #2, how would go you about prioritizing repairs at the other two steps?

Reference no: EM1338399

Questions Cloud

Zero growth valuation models : In each of the following situations assume a zero-growth rate for earnings and dividends (NPVGO is zero), that all earnings are paid out as dividends, and that the earnings-based valuation model is being used.
Human emotion and progress : Write a paragraph describing the: Issue, Expected impact
Explain entrepreneurial organization : Explain Entrepreneurial organization and Describe how an entrepreneurial organization's size and age and growth goals are influential in determining its character and strategic direction
Describe the output level of the firm : Describe the output level of the firm, the number of workers it employs and the profit of the firm.
Critical path of a pert chart : In terms of creating a timeline, what is meant by the critical path of a PERT chart?
Successful strategy implementation : You decide that the client needs an overview of how classic management activities - planning, organizing, controlling, and leading - enable successful strategy implementation.
Explain the solution to strategic management questions : Explain The solution to strategic management questions and Discuss some of the requirements for successful strategic change
Computing float for activity : What is the float for Activity I?
Minimize costs : Assign jobs to machines to minimize costs.

Reviews

Write a Review

Project Management Questions & Answers

  Estimates critical to effective project management

Why are accurate estimates critical to effective project management? Please explain in detail.

  Computing minimum total direct cost for project durations

Compute the minimum total direct cost for each of the following project durations (based on the cost associated with each activity): 13, 14, 15, 16, 17, and 18 weeks.

  Evaluate the performance of each project proposal

To evaluate the performance of each project proposal with respect to their Overall

  Computing activity slack and identifying the critical path

Complete the forward and backward pass, compute the activity slack, and identify the critical path.

  Key planning priorities useful in completing team project

Write key planning priorities that could be most useful in completing a Team Project.

  Determining the annual net cash flows

If the firm is in the 40 percent marginal tax bracket, determine the annual net cash flows generated by the drill press.

  Test hypothesis using data

A writing an article about call centre working conditions a reporter has claimed that the average tenure is no more than two years. Formulate and test a hypothesis using these data to determine if this claim can be disputed.

  Develop maut model and ahp model

Develop a MAUT model to assist in the selection process. Develop an AHP model to assist in the selection process.

  Risk identification with project contingency planning

How does risk identification help with project contingency planning?

  Purchasing in consumer and business markets

What are the key differences between purchasing in consumer and business markets? The buying centre refers to all the individuals and units participating in business purchase decisions.

  Calculating company-s profit at each level of production

Calculate company's profit at each level of production. Assume that the company will sell all of its output. At what production level is profit maximized?

  Analyzing firm-s commitment to quality

You are to choose a publicly-traded company and analyze the firm's commitment to quality, based upon the principles learned in this course.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd