A project has the following activities, precedence relationships, and time estimates in days:
Activity Predecessor Optimistic Most likely PessimisticActivities Time Time TimeA -- 6 7 8B A 4 4 4C A 5 6 8D B 8 10 10E B 7 10 15F C 9 9 13G C 7 7 7H D 4 6 8I E, F 6 9 11J G 8 9 10K H, I, J 3 5 6
Compute the earliest start, earliest finish, latest start, latest finish, and slack for each activity
What are the critical path and duration of the project?
What is the probability that the project will take longer than 38 days?
Discuss a performance improvement project you have been involved in or had knowledge of.
Explain the five steps of Project Interface Management and whether they are applicable at the project level or the portfolio/program level.
What are the organizational strengths and weaknesses?
In spite of their poor cost performance, why do you think these projects were supported to their conclusion? What would it take to kill a high-visibility project such as these?
Determine the expected time and variance for each activity.
Criticism of traditional measures of performance
Which type of organizational form fosters teamwork in the best manner?
What are the two most important abilities a good project manager should have?
What is involved in preparing a business case for a project?
Find the critical path and project duration in days. Given that each resource is assigned 100% to each task, identify the resource constraints.
You are required to submit a written assignment relating to New Product Development.
Which of the following is a step in the directing process?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd