Create a work breakdown structure

Assignment Help Project Management
Reference no: EM132147787

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your company's project management standards, you are required to conduct the following activities.

1. Create a Work Breakdown Structure (WBS) that lists all tasks required for this project. Specifically,
- Construct the WBS in a tabular form
- Provide four levels of detail
- Describe best practices in general for constructing a good WBS (Note: additional research on this topic beyond the textbook is strongly encouraged)
- Articulate what best practices have been utilized in this assignment and what have not due to the constraints of this assignment

2. Develop a WBS dictionary to briefly describe each work package
3. Estimate duration for each work package, sequence activities at the work package level, and construct a Gantt Chart for this project

The assignment should be submitted according to the following requirements. Any submission that does not follow these requirements will be discounted.

- Due Date and Time: Sunday, Oct 28th, 11:00 PM
- Format: Single-spaced; 12 Point Times New Roman font; One inch margins
- Number of Pages: Not to exceed 5 pages. The 5-page limit includes supporting materials such as references, figures, or charts
- Student Name: Your name should be listed on the top-right corner of the first page
- Citations: Clear citations should be provided, in APA format, when applicable for all work that is not your own

Verified Expert

The solution file is prepared in ms project to create a work break down structure for upgrade 200 desktop to windows 10 in the tabular form. The work break down structure has four levels with details of sub task and discussed best practices in general for constructing a good WBS. Also discusses about Articulate what best practices have been utilized in this assignment and what have not due to the constraints of this assignment. The solution has all screen shots of work break down structure and gantt chart and references are included as per APA format.

Reference no: EM132147787

Questions Cloud

Overlook the on-boarding of new employees : Why do organizations so frequently overlook the on-boarding of new employees?
What is intrapreneurship : What is intrapreneurship? and How can it be enabled in an organization?
How is continuous improvement related to innovation : Total quality management involves a continuous improvement approach. 1. How is continuous improvement related to innovation?
Scoreboard approach has gained popularity in recent years : The balanced scoreboard approach has gained popularity in recent years. What is this approach and how does it integrate strategic and operational control?
Create a work breakdown structure : IS 669 Project Management Operations - Create a Work Breakdown Structure (WBS) that lists all tasks required for this project
What are the pros and cons of each : 1. Why is strategic control important in the strategy implementation process?
Develop a process map about the prescription filling process : Develop a process map about the prescription filling process for HMO's pharmacy, in which you specify the key problems .
What kind of challenges and opportunities : What kind of challenges and opportunities is Four Seasons Hotels facing in terms of processes and lateral capabilities?
Organizational and environmental pressures : What are the similarities of organizational and environmental pressures?

Reviews

urv2147787

11/29/2018 1:42:21 AM

Amazing job dear experts and thanks a lot to expertsmind to avail me such expert who followed every units instruction perfectly. I really amazed with the grades I received with your help. I am really thankful. I have passed the class with A grade. You are true lifesaver.

len2147787

10/23/2018 3:55:15 AM

The assignment should be submitted according to the following requirements. Any submission that does not follow these requirements will be discounted. Due Date and Time: Sunday, 28th, 11:00 PM Format: Single-spaced; 12 Point Times New Roman font; One inch margins Number of Pages: Not to exceed 5 pages. The 5-page limit includes supporting materials such as references, figures, or charts Student Name: Your name should be listed on the top-right corner of the first page Citations: Clear citations should be provided, in APA format, when applicable for all work that is not your own

len2147787

10/23/2018 3:54:58 AM

A good WBS needs to incorporate both PM concepts and realistic tasks to complete the project. First, this is a project manager class. Students from this class are encouraged to think more like project managers than engineers. Example of PM concepts that would be covered in the WBS include project integration, scope definition, monitoring, etc. Next, please include realistic tasks that will lead to the completion of this specific project, rather than general tasks that could apply to any project. A typical question one would ask after finishing a draft WBS is "If one were to transfer the WBS to another project manager, would he or she be able to finish the project?"

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd