Reference no: EM131228705
Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information, Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks.
Tasks:
1. Create a risk register for the project, using Table 11-5 (from the Schwalbe text) and the data after it. Identify eight potential risks (for team of 4) or six potential risks (for team of 3), including risks related to the problems described in the opening paragraph above or any risk that you consider would have an impact on the success of this project. Include negative and positive risks.
2. Plot all the risks, identified in Task 1, on a probability/impact matrix, using Figure 11-5 (from the Schwalbe text). Also assign a numeric value for the probability and impact of each risk on meeting the main project objective. Use a scale of 1 to 10 in assigning the values, with 1 representing the lowest values. For a simple risk factor calculation, multiply the probability score and the impact score. Add a column called Risk Score to your risk register to the right of the impact column. Enter the new data in the risk register. Write your rationale for how you determined the scores for each of the risks.
3. Develop a response strategy for each of the risks you have identified in Task 1. Enter the information in the risk register (from Task 1). Also write a separate paragraph describing what specific tasks would be required to implement the strategy. Include time and cost estimates for each strategy as well.
|
Explain the sarbanes-oxley act
: For this essay, you will conduct research in order to contrast agency theory and stewardship theory in corporate governance. Explain the Sarbanes-Oxley Act and its impact on corporate governance. How has it changed the way leaders do business in the ..
|
|
What coaching techniques can be used with the team
: How is the Scrum Master role similar and different than a project manager role? What “coaching” techniques can be used with the team?
|
|
About the dvd sales
: DVD Sales Hans Hultgren, the sales manager for DVD Sales, wants to maximize his profit on the sale of portable DVD players. He already has two portable models he plans to sell: Hans needs your help in calculating his maximum profit. First, he would l..
|
|
Identify all outstanding security interests in the aircraft
: You are in the market to buy an aircraft and have identified one that appears that it would meet your needs and is in your price range. determine who owns the aircraft, identify all outstanding security interests in the aircraft,
|
|
Create a risk register for the project
: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Create a risk r..
|
|
Facing interesting strategic issues
: Select either a publicly-held corporation or a private company (where the financial data is accessible) that is facing interesting strategic issues. The use of a publicly-held firm rather than one that is closely-held may be important to ensure adequ..
|
|
What are the basic elements of outbacks plan
: Write a brief assessment (two pages) of the Outback Steakhouse case found in the text. Pay particular attention to the following questions: What are the basic elements of Outback's plan for going international? What do you see as the strengths and we..
|
|
Bowing to pressure from consumer? groups
: ?Harley-Davidson allows Portland Clothing to stitch the Harley logo on the jackets it makes and sells to retailers. This is a? _________ arrangement. Bowing to pressure from consumer? groups, McDonald's now offers alternatives to french fries in its?..
|
|
Recommend strategies to reduce cost and legal liabilities
: The St. Clare Hospital was founded in 1988. In the past few years, the revenues have dropped steadily to a point where CEO James Edwards is considering cost control to improve the organization's bottom line. Describe types of conflict indentified in ..
|