Project Management Exercise -
The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The results of their meeting are found in the following table.
Activity
Description
Duration
Predecessor
1
Define Scope
6
None
2
Define Customer Problems
3
Define data records and relationship
5
4
Mass Storage Requirements
2, 3
Consultant Needs Analysis
11
Prepare Installation Network
7
Estimate Costs and Budgets
8
Design Section Point System
4, 5
9
Write Request Proposal
10
Compile Vendor List
Prepare MGMT Control System
6, 7
12
Prepare Comparison Report
9, 10
13
Compare System Philosophies
8, 12
14
Compare Total Installation
15
Compare Cost of Support
16
Compare Customer Satisfaction Level
17
Assign Philosophies Points
18
Assign Installation Cost
19
Assign Support Cost
20
Assign Customer Satisfaction Points
21
Select Best System
11, 17, 18, 19, 20
22
Order System
The project team has requested that you create a network diagram for the project, identify the critical path, and determine if the project can be completed in 50 weeks.
You are to first do a "hand drawn" solution, and then use Microsoft Project to create network diagram again. Assumptions: Start date is October 3, 2016, one shift per day, no overtime, no weekends, and all traditional holidays to be observed.
Assignment: Project Planning - Developing the Project Plan and Determining Critical Path Using the excel sheet provided, create a project plan for the District 4 Warehouse Move project
communication barriers to effective communicationsuppose you are speaking to a group of employees which communication
Write a paper which explore Results Based Management topic and how it plays the role of project management in development.
vendor risk in projectsone of the risks you anticipated for a project was the late delivery of the prototype from the
Was this communication method effective and what would have been the best way to communicate the change to the employees and why?
Define the importance of purchasing and supply management and how this relates to selecting a qualified supplier. Discuss how to select strategies for negotiating prices.
What is the difference between leadership and management? How do these two terms relate to a project manager and what are the four frames of organizations? Describe each frame.
project engagementone view suggests that engagement is the key to good implementation. in fact one view takes the
Project Topics- Following are the topics for final project. You are supposed to pick one topic for your project. A study of the practices of two MNCs. A study of World Trade Organization (WTO) and Free Trade Agreements (FTA) and A study of the two di..
Identify two IT - related projects that would be consistent with this plan. Recommend one of the two projects for implementation. (Hint: choose a publicly traded company to ensure that you can find sufficient information to develop the strategic ..
Write a paper on how the study of project cost management will help the project manager to make better choices. Organize your paper in the following sections: Background - Summarize the situation. Issues - Identify the matters of concern
Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance. Summarize in words what you see project status to beat this time.What do you predict regarding the final cost and final ..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd