Create a network diagram for the project

Assignment Help Project Management
Reference no: EM131227678

Project Management Exercise -

The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The results of their meeting are found in the following table.

Activity

Description

Duration

Predecessor

1

Define Scope

6

None

2

Define Customer Problems

3

1

3

Define data records and relationship

5

1

4

Mass Storage Requirements

5

2, 3

5

Consultant Needs Analysis

11

2, 3

6

Prepare Installation Network

3

4

7

Estimate Costs and Budgets

2

4

8

Design Section Point System

1

4, 5

9

Write Request Proposal

5

5

10

Compile Vendor List

2

5

11

Prepare MGMT Control System

5

6, 7

12

Prepare Comparison Report

5

9, 10

13

Compare System Philosophies

5

8, 12

14

Compare Total Installation

2

8, 12

15

Compare Cost of Support

3

12

16

Compare Customer Satisfaction Level

8

12

17

Assign Philosophies Points

1

13

18

Assign Installation Cost

1

14

19

Assign Support Cost

1

15

20

Assign Customer Satisfaction Points

1

16

21

Select Best System

2

11, 17, 18, 19, 20

22

Order System

1

21

The project team has requested that you create a network diagram for the project, identify the critical path, and determine if the project can be completed in 50 weeks.

You are to first do a "hand drawn" solution, and then use Microsoft Project to create network diagram again. Assumptions: Start date is October 3, 2016, one shift per day, no overtime, no weekends, and all traditional holidays to be observed.

Reference no: EM131227678

Questions Cloud

Create it department to support agcredit future architecture : What new internal IT capabilities will have to be developed in order to create an IT department to support AgCredit's future business architecture?
Type of packet filter : What type of packet filter would you be most likely to recommend: stateless, stateful, or one that looks at packet content? Why?
Important aspect of maintaining business longevity : Physical security is a very important aspect of maintaining business longevity. Picture the following example: a building located downtown holds the information on numerous businesses run by an overhead business within the same building.
Evaluate and describe any cultural considerations : This person might be a political, business, human rights, education, or entertainment figure. Examine the major theoretical approaches studied in the class so far (psychodynamic, behavioral, learning, trait and type, and humanistic). Briefly descr..
Create a network diagram for the project : The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The project team has requested that you create a network diagram for the project, identif..
Find the electric field intensity at a point : 1. If V=2x2-3y2+z2 represents the electrostatic potential at a joint, find the electric field intensity at a point (3, 2, -3). A vector field is given as, F=iy+j(x+y2)+k(yz+zx) Find: (i) div (F) (ii) curl (F). Show that F=i(x+y)+j(x+y)+(y-z) represen..
Digital evidence collection : Like most people, you probably travel familiar paths every day. When you walk down a street in your neighborhood or drive to work, do you feel that you could travel these routes easily while blindfolded? How would you feel if fog covered your fami..
Identity affects an individual''s life-span development : Add to your colleague's explanation of how gender identity affects an individual's life-span development. Explain whether you might use your colleague's strategy for applying the concept of gender identity to social work practice. Provide support f..
Experimental traceroute that uses fewer messages : Traceroute uses 2n messages each time it's run; find an experimental traceroute that uses fewer messages and explain how it works. Run traceroute for the gwu.edu and amazon.com for mac, and explain the results. Again, an explanation is needed fo..

Reviews

Write a Review

Project Management Questions & Answers

  Developing the project plan and determining critical path

Assignment: Project Planning - Developing the Project Plan and Determining Critical Path Using the excel sheet provided, create a project plan for the District 4 Warehouse Move project

  Communication barriers to effective communicationsuppose

communication barriers to effective communicationsuppose you are speaking to a group of employees which communication

  Role of project management in development

Write a paper which explore Results Based Management topic and how it plays the role of project management in development.

  Vendor risk in projectsone of the risks you anticipated for

vendor risk in projectsone of the risks you anticipated for a project was the late delivery of the prototype from the

  Show the organizational change communication

Was this communication method effective and what would have been the best way to communicate the change to the employees and why?

  Define the importance of purchasing and supply management

Define the importance of purchasing and supply management and how this relates to selecting a qualified supplier. Discuss how to select strategies for negotiating prices.

  What is a work breakdown structure

What is the difference between leadership and management? How do these two terms relate to a project manager and what are the four frames of organizations? Describe each frame.

  Project engagementone view suggests that engagement is the

project engagementone view suggests that engagement is the key to good implementation. in fact one view takes the

  Study of world trade organization and free trade agreements

Project Topics- Following are the topics for final project. You are supposed to pick one topic for your project. A study of the practices of two MNCs. A study of World Trade Organization (WTO) and Free Trade Agreements (FTA) and A study of the two di..

  Identify two it - related projects

Identify two IT - related projects that would be consistent with this plan. Recommend one of the two projects for implementation. (Hint: choose a publicly traded company to ensure that you can find sufficient information to develop the strategic ..

  Write a paper on how the study of project cost management

Write a paper on how the study of project cost management will help the project manager to make better choices. Organize your paper in the following sections: Background - Summarize the situation. Issues - Identify the matters of concern

  Createa gantt chart from the work break down structure

Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance. Summarize in words what you see project status to beat this time.What do you predict regarding the final cost and final ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd