Cost of production report using FIFO(equivalent production)

Bangor Products manufactures electronics language translators. Analysis of beginning Work in Process Inventory for July 2008 revealed the following:

800 Units Percent Complete Cost Incurred
Direct Material 45% 6,748
Direct Labor 65% 8,680
Overhead 40% 5,710
Total Beginning Inventory 21,138

Direct Labor costs were extremely high during June because the company had a labor strike and paid a high premium for production that month.

During July, Bangor Products started production of another 11,400 translators and incurred $259,012 for material, $58,200 for direct labor, and $188,210 for overhead. At the end of July, the company had 400 units in process (70% complete as to material, 90% complete as to direct labor, and 80% complete as to overhead).

A.) Prepare a cost of production report for July using the FIFO method of the process costing

Reference no: EM13363452

Questions Cloud

1how did the virginia plan the new jersey plan the great : 1.how did the virginia plan the new jersey plan the great compromise and the three-fifths compromise lead our current
Case of a member of a manager-managed llceric is a member : case of a member of a manager-managed llceric is a member of a manager-managed llc but is not a manager. this llc
Design and implement a library system that does the : design and implement a library system that does the following ? takes details of a studentlibrary users first name last
Manager-managed llclynda is a member of a manager-managed : manager-managed llclynda is a member of a manager-managed llc but is not a manager. however lynda has considerable
Cost of production report using fifoequivalent : cost of production report using fifoequivalent productionbangor products manufactures electronics language translators.
Expatriate manager1 would you recommend hiring a local : expatriate manager1. would you recommend hiring a local manager over an expatriate manager? why? does the phase of the
Short answer and short problems1nbspnbspnbspnbspnbsp : short answer and short problems1.nbspnbspnbspnbspnbsp briefly discuss the most important factors limiting the
Pmi and it project team roles are notedif a person has been : pmi and it project team roles are noted.if a person has been certified by the pmi but has never been on an it project
Pert chartthe project management chart that graphically : pert chartthe project management chart that graphically models the sequence of project tasks and their

Reviews

Write a Review

Project Management Questions & Answers

  Type of organizational form fosters teamwork

Which type of organizational form fosters teamwork in the best manner?

  Pmi chapter meetingyou are attending your local pmi chapter

pmi chapter meetingyou are attending your local pmi chapter meeting. fortunately it draws project managers from many

  Developing a budget number around project schedule

Develop a budget number around our project schedule, be sure to include your constraints and the alternatives you can use to overcome these constraints.

  Implications of completing project before scheduled date

What are some implications of completing a project before the scheduled completion date?

  Project management affect success of project outcome

The benefits of project planning, project management within the various types of organizational systems, and how your approach to project management will affect the success of the project outcome.

  What types of information can we learn about a project by

what types of information can we learn about a project by reviewing the project schedule and all the information used

  Identify the risk the impact expected outcomethe course is

identify the risk the impact expected outcomethe course is corporate risk management.1 i have to make a risk register

  Computer breakeven cash inflows for etsitty arts incs new

computer breakeven cash inflows for etsitty arts incs new projectetsitty arts inc. a leading producer of fine cast

  Project management and risk

Both internal and external factors need to be addressed as well as the probability and impact that certain risks could have on a particular project.

  Describe the term group after discussion

Describe the term group after discussion with your fellow team members and avoid repeating a dictionary definition

  Discuss a situation from your own experience

discuss a situation from your own experience, in which that objective should be given more importance than the other two

  Prepare the case for an optimistic sales manager

Prepare the case for an optimistic sales manager who suggests that you should move ahead with the FMS now

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd