Construction Economics and Procurement Assignment

Assignment Help Project Management
Reference no: EM132393641

Construction Economics and Procurement Assignment - Edinburgh Tram Extension

School of the Engineering and Built Environment, Glasgow Caledonian University

Assignment Brief - This assignment is based on the proposed extension to the Edinburgh Tram system from York Place through to Newhaven.

Task -

Estimate the impact of the project on the local economy during the construction phase. This should focus on the direct, indirect and induced effects of the works on: Gross Domestic Product, Employment, Income, and Imports. Use the Input-Output Tables for Scotland provided for the basic estimate making any adjustments deemed necessary. The negative impacts of the construction including traffic disruption should be considered. Please state any assumptions made.

This deals essentially with backward linkages from the construction works to the local economy in terms of output, expenditure and jobs created.

The key thing about spending on construction is that it is temporary. Hence expenditure of £60 million in one year will lead to increases. However, if the expenditure is at £55 million the next year, this will equate to a reduction of £5 million. So over the profile of the project, spending, jobs, imports etc., will end up exactly where they started.

Year

Dates

Actions

Construction Spend

2017

Q4

Tendering Process

£1 million

2018

To Q4

Tendering Process

£1 million

2018

From Q4

Preparation

£4 million

2019

From Q2

Construction

£15 million

2020

Q1 to Q4

Construction

£55 million

2021

Q1 to Q4

Construction

£78 million

2022

To Q1

Testing

£11 million

2022

From Q2

Operation

-

Total

165 million

Notional capital spending pattern

The expenditure on construction for the development plan for each of the years of the development plan is given above. The increase in construction output brought about by the investment programme in 2017 (£1 million) should be inserted in cell B12 of the sheet "Construction". This will enable the direct implications on Employment, Income, GDP, and Imports to be read from cells F20, G20, P20, and V20 respectively.

These are limited to the direct effects of the construction work. If the direct plus indirect effects are needed, the results can be read from D39, F39, H39, and J39 respectively. This will incorporate the implications on other industries such as materials supply from the additional construction work.

This will generate additional income throughout the economy. The direct plus indirect plus induced effects can be read from cells D58, F58, H58, and J58 respectively.

Insert the annual spend (in £ million) in Cell B12 of Construction. The main figures on spending etc. can be read off the sheet (in £ million). The impact on employment can be read (in thousands) from cells F20, D39 and D58.

For the second year (2018) the increase in construction output from 2018 will be £4 million. That is a total spend of £5 million (£1 million tendering plus £4 million preparation) less £1 million for 2017.

This can be inserted in cell B12 of a new sheet based on 'Construction'. The above process should be repeated.

For the third year (2019) the increase in construction output will be £10 million (£15 million less £5 million). By 2021, the construction spend will have peaked. By 2022, the output should fall by £67 million (£78 million less £11 million). This should be inserted into cell B12 of a new sheet as a negative number.

Some adjustment may be taken for the negative effects of the construction process, on the key economic variables, including road closures and partial closures.

Please note that a project of this type would normally involve significant imports from the Rest of the World (RoW) as the trams concerned were manufactured in Spain by CAF, and the electrical equipment plus signalling gear and rails would almost certainly have been imported from RoW. However, in this instance all such equipment is already in the possession of Lothian Trams having been purchased under the previous contract and stored. Lothian Trams have more than enough trams to service this extension and beyond. Hence the costs of such are not required to be considered.

Note - After finish the report, make 7 slide presentations.

Attachment:- Construction Economics and Procurement Assignment Files.rar

Reference no: EM132393641

Questions Cloud

Explain why employment legislation exists : Explain why employment legislation exists. How might employers play a key role in preventing the need for additional employment legislation? Describe in detail.
Explain the influence of governance and ethics : Weeks 3, 4 and 5 Individual Assignments are integrated to generate a Strategic Management Plan. This is part three of the three part Strategic Management Plan.
How should we prevent mass shootings in the workplace : How should we prevent mass shootings in the workplace? Choose your own topic - email me for approval of an issue not on this list. Narrow down your issue focus.
Explain the significance of ethnicity and sexual orientation : The purposes of this assignment are to enhance your understandings in the elements, activities, and impacts of intercultural training and abilities to.
Construction Economics and Procurement Assignment : Construction Economics and Procurement Assignment - Edinburgh Tram Extension. Glasgow Caledonian University. Estimate impact of the project on local economy
Discuss the rationale for performance appraisal methods : Select two distinct jobs of your choice. Go to the Occupational Information Network (O*NET). Review the major tasks for each job. Then, for each job.
What responsibilities do you have for your patients : As a health care manager, what responsibilities do you have to uphold these for your patients? Provide an example to illustrate your role and responsibility.
System development life cycle : Now that you assessed the business, identified some of the inefficient HR related processes plaguing Larson Property Management Company,
How you have determined budget associated with project costs : Explain to the management team and your project team how you have determined the budget associated with project costs. How are costs aggregated?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd