Time Management - Scheduling
Your project team presented you with the above information. You now need to:
1. Construct the PERT Network Diagram
2. State the Critical Path of the project
3. Present the ES, EF, LS, LF and Slack for activities B, D & F
4. Calculate and state the variance for the project
5. Calculate and state the standard deviation for the project
6. The sponsor for the project would like to know the probability of completing the project within 30 days. Kindly calculate and state this in percentage.
ACTIVITY
PREDECESSOR
OPTIMISTIC TIME
NORMAL TIME
PESSIMISTIC TIME
A
-
6
5
10
B
9.2
C
10.6
8
16.2
D
9.8
7.3
10.02
E
B, C
10.3
5.5
11.68
F
4
13
G
9.1
20.1
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd