Construct a network schedule for the stadium project

Assignment Help Project Management
Reference no: EM131892009

Greendale Stadium Case

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ASSIGNMENT

Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:

Will the project be able to be completed by the May 20 deadline? How long will it take?

What is the critical path for the project?

Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days).

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).

The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

Greendale Project ReDux

This assignment consists of two (2) parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule

(Submit as one [1] Microsoft Project file)

Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the "Greendale Stadium Case" located at the end of Chapter 6, and incorporating the following constraints.

Note: When you create your MS Project schedule, you will need to update your project per the following constraints:

The project must consist of at least twenty (20) tasks.

Each task must have a start and finish date that matches the duration noted in the assignment.

Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew).

Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day).

In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day,Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve.

Part B: Written Response

(Submit as a Microsoft Word file)

Respond to the following questions in a one to two (1-2) page paper based on your project schedule.

When will the project be completed?

What is the critical path for the project?

How much slack / float is in your project? What activities have the greatest slack / float?

Identify the top three (3) activities that you believe could impact the project completion date.

What additional activities you would add to this project to make it more complete, from a project management viewpoint?

Format your assignment according to the following formatting requirements:

Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

Include a cover page containing the title of the assignment, the student's name, the professor's name, the course title, and the date. The cover page is not included in the required page length.

Reference no: EM131892009

Questions Cloud

Discuss potential problems with the use of IRR : The use of NPV as an investment criterion is said to be more reliable than using IRR. Discuss potential problems with the use of IRR.
Review problem regarding philosophy games : About 500 words. Take any 2 games of your choice, reflect on the results and your reasoning throughout. Summarize your reflection on your reasoning.
What is the bond yield to maturity : What is the bond’s yield to maturity (YTM) on June 30, 2018, if the bond sold for $963 on that date?
Problem weight of equity : What weight should you use for debt in the computation of OMG’s WACC?
Construct a network schedule for the stadium project : construct a network schedule for the stadium project and answer the following questions:What is the critical path for the project?
Briefly define and describe the core principles of ia : Briefly define and describe the core principles of information assurance (IA). Be sure to utilize multiple sources in order to gain a broad spectrum.
Magnitude and direction of the ball velocity : Using the approximate value of g = 10 m/s2, what are the magnitude and direction of the ball's velocity at the following times?
Reestimate beta with this new data point : Suppose that you add 1 more month of data to your spreadsheet and find that in October 2010, Fors was down 5% while the market was up 5%.
Assume the expectations hypothesis holds : Assume the expectations hypothesis holds. What is the expected price of this bond 6 months from today,

Reviews

Write a Review

Project Management Questions & Answers

  What should writer strive to do in body of a formal report

What should the writer strive to do in the body of a formal report? -  What is the purpose of references or works cited?

  Consider three cases of variation in the model parameters

Bell assumed with certainty that the ordering cost is $543 per order and the inventory carrying cost is $210 per unit per year.

  Explain why its earnings may be lower initially

If Sue decides to expand CHC's existing facilities, explain why its earnings may be lower initially? A health club differs from manufacturing firms in that it produces a service rather than products.

  What were the solutions used to address the problem

What were the solutions used to address the problem? Was the case you described a special-cause or common-cause? Do you feel the solution or approach used appropriate for the cause?

  How do develop quality questions for use in a survey

How do develop quality questions for use in a survey - what is necessary in order to develop proper questions for utilized in a survey product.

  Effective project managementwhat was the project and

effective project managementwhat was the project and briefly describe whether or not the project was successful. what

  Will ames be able to collect damages from bowen

The next day, without knowledge or notice of Bowen's contract with Curd, Ames began construction. Bowen ordered Ames from the premises and refused to allow him to continue. Will Ames be able to collect damages from Bowen? Explain.

  What balancing test does the court employ

What balancing test does the court employ in determining whether an employee's act of violence justifies the employee's dismissal?

  State the purposes of the two main federal securities laws

What was the stimulus for the creation of securities regulation?-  State the purposes of the two main federal securities laws.

  Multicultural management in virtual project setting

Write a proposal for multicultural management in the virtual project setting.

  Develop a goal setting table with three deliverables

Based on Brooks role and responsibility, develop a goal setting table with at least three deliverables that could be used for his performance review with his manager to help him build his case for a fair promotion opportunity.

  What is annual demand for a single item d

A production process is used to produce 20 different items, under intermittent batch production.  When inventory or projected inventory of an item drops to a certain level, a production order is released for Q units of that item.  Because product dem..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd