Construct a network diagram, identify the critical path
The following data were obtained from a project to build a pressure vessel:
Activity Duration PredecessorsA 4 weeks ---B 4 weeks ---C 3 weeks BD 2 weeks A, CE 3 weeks BF 5 weeks D, E, GG 2 weeks BH 6 weeks FI 3 weeks GJ 1 week I
Construct a network for the project. Then review and answer (A) and (B).
(A.) Evaluate the scheduled completion time and identify the critical path.
(B.) What is the slack time (float) for activities A, D, E, and G?
What is the definition of a project? What are some of the elements that differentiate a project from maintenance work and how does a focus of a project affect the business direction and orientation?
suitability and reliability in qualitysuitability and reliability are two examples of quality in terms of buying
Suppose an asset is sold for less than its book value at the end of a projects life, and generates a loss that is fully deductible from the firm's ordinary income.
What are some ways to overcome the fear of losing control in these situations and what are some suggestions you can give when it comes to working in teams and dealing with communication in a virtual team?
On May 18, of last year, Carter sells unlisted stock with a cost of $24,000 for $60,000. Carter collects $20,000 initially and is scheduled to receive $10,000 each year for four years starting this year plus an acceptable rate of interest.
Lauren Moore has sold her business for $500,000 and wants to invest in condominium units (which she intends to rent) and land (which she will lease to a farmer).
Describe the role of project management in modern organizations. Use effective communication techniques.
Prepare a production budget for the second quarter of the year.
discuss processes involved in determining and managing project budgets explain points and pitfalls to keep in
social analytics trade-offs in project planexplain what advantages does a cio bring to a business? what might be two
Find the crash cost per week for each activity and record the results in the crash table in the table. What are the total normal costs for the project?
Question about Aggregate production planning - Determine the total cost using a one-month planning horizon
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd