Construct a network diagram, identify the critical path
The following data were obtained from a project to build a pressure vessel:
Activity Duration PredecessorsA 4 weeks ---B 4 weeks ---C 3 weeks BD 2 weeks A, CE 3 weeks BF 5 weeks D, E, GG 2 weeks BH 6 weeks FI 3 weeks GJ 1 week I
Construct a network for the project. Then review and answer (A) and (B).
(A.) Evaluate the scheduled completion time and identify the critical path.
(B.) What is the slack time (float) for activities A, D, E, and G?
Explain what are the responsibilities of a project manager in a matrix-type organization and what about project-type organizations? Are there any differences?
Explain how do you ensure that the requirements are fully developed and vetted by project SMEs so that the risk of a scope increase is low?
In your opinion what are the key elements of the reporting process?
Why do you think organizations tend to ignore post-project evaluations and how could the concept of making such evaluations mandatory be implemented
Many will argue that it is considered a good practice to acknowledge the limitation of your research/project.
Evaluate the technological components of the production process and determine which provides the greatest overall benefit. Explain your rationale.
Identify and briefly describe some of the "non-numerical" factors that cause fluctuations in demand for the iPhone 4.
Develop a risk management plan for school as a school authority - take an example of the recent gun shoot incident in the United States.
Given EVM data, estimate the cost at completion of a project using the method "EAC based on Combined Cost and Schedule Performance.
What are the differences between qualitative and quantitative risk analysis? Explain.
Preventative measures a project manager can take to manage resources - Describe what factors might intervene between a project plan and its execution to disrupt the resources assigned to the project.
Use GM (General Motors) as an example, explain variable, fixed, average, marginal, and total cost of production.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd