Construct a network diagram and find the critical path

Assignment Help Project Management
Reference no: EM1343334

Construct a network diagram, identify the critical path

The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors
A 4 weeks ---
B 4 weeks ---
C 3 weeks B
D 2 weeks A, C
E 3 weeks B
F 5 weeks D, E, G
G 2 weeks B
H 6 weeks F
I 3 weeks G
J 1 week I

Construct a network for the project. Then review and answer (A) and (B).

(A.) Evaluate the scheduled completion time and identify the critical path.

(B.) What is the slack time (float) for activities A, D, E, and G?

Reference no: EM1343334

Questions Cloud

Project analysis and evaluation : the projects cash flow estimates are real or nominal and is the 14.5% cost of capital a real or nominal rate? Is the current NPV biased, and if so, in which direction?
Institutional theories- functional and product matrix : Summarize the theorists arguments concerning the practical institutional theories of functional and matrix forms of organization
Critical path of a pert chart : Project Timelines - Critical Path and PERT - In terms of creating a timeline, what is understand by the critical path of a PERT chart
Project management - value of linear reponsibility matrix : Project management: Value of linear reponsibility matrix - use the RAM meaning the responsibility assignment matrix
Construct a network diagram and find the critical path : Evaluate the scheduled completion time and identify the critical path and what is the slack time (float) for activities A, D, E, and G
Describe the role of project manager : Describe the role of a project manager as an interface between business and technology professionals in an organization.
Prepare a comprehensive project scope analysis : The conceptual development process, scope statement and statement of work that will clearly detail the projects expectation , problems , goals, objective, and aids in the projects communications with stake holders
What is the most important problem facing visa : What recommendations would you make to VISA and in what order of priorities and how do you balance between your commitment to shareholders and your commitment to the community
Show the project complexity : Project complexity - How and why does that organization evaluate project complexity and what factors are typically considered

Reviews

Write a Review

 

Project Management Questions & Answers

  Project management-schedule, budget, cost estimation

Prepare a project schedule in Microsoft Project 2007 and explain the rationale behind time and cost estimation methods and why you would chose one method over another

  Show the project complexity

Project complexity - How and why does that organization evaluate project complexity and what factors are typically considered

  Activities involved as project manager in relocating company

What are the activities involved as the project manager in relocating a company. (I am looking for a breakdown of the process involved.)

  Defining network and critical path

Draw the network. What is the critical path?

  Create a project organisation chart

Explain what information is most and least useful to a project leader when creating a project organization chart

  Enhancing steps associated with reengineering

Select the PERT technique you consider LEAST valuable when altering or enhancing steps associated with reengineering. Explain your choice. Describe and analyze how the two techniques you chose influence the Critical Path Method.

  Ways in which project selection affects risk

What are some ways in which project selection affects risk? How can these risks can be reduced?

  Tax consequences from sale of the asset

The tax consequences from the sale of the asset will be?

  Grade-seven generalist evaluate grade -twelve specialist

What information can the project manager base his or her evaluation? Can a grade-7 generalist evaluate a grade -12 specialist?

  Write a proposal for multicultural management

- Identify the most critical issues faced by managers with regard to the topic and outline solutions to the issues you identify using theories and best practices presented ininternational business subjects.

  Explaining member of a manager-managed llc

Eric is a member of a manager-managed LLC but is not a manager. This LLC invests in real estate and manages it as rental property in a college town.

  Control schedule and control cost processes

Issues to be covered are: The need within your organization; Your idea for control schedule and control cost processes to be implemented.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd