Question 1

By carefully considering the objectives for this project, critically discuss the likely details of the business case highlighting the key issues (you may ignore any financial considerations).

Question 2

Collaboration is probably the most important factor of a successful project, as well as to mitigate potential risks. Critically discuss how early collaboration might help to consider and reduce the risks in this project?

Question 3

The building was constructed with a complex steel frame and the use of concrete slabs to provide flooring, stair, and lift towers. Steel and concrete teams were often working at the same time with one following on right behind the other in order to deliver the building on time. A critical element to the project timeline was the initial substructure which had 20 weeks allocated to it. This section included the foundations, construction of the leisure centre's pool and the associated pipe work.

Activities for the substructure are shown in the table. Times are shown in weeks, where O= Optimistic time, P= Pessimistic time, ML= Most Likely time.


Activity

O

P

ML

Precedence

1

Site clearance

3

5

4

 

2

Excavation

4

5

4

1

3

Piling

3

5

3

2

4

Drainage

3

6

4

2

5

Pump housings

3

3.5

3

2

6

Sub soil layer

0.5

1.5

1

3

7

Steel formwork

2

2

2

6

8

Steel reinforcement

1

1.5

1

7

9

Initial electrical work

2

4

2

5

10

Initial necessary plumbing

2

3

2

4,9

11

Concrete

0.2

1

0.5

8,10

12

Concrete cure

3

4

3

11

Working to one decimal place:

a. Calculated the likelihood that this part of the project can be completed on time.
b. Find out the time that the project manager might be 95% confident of completing by
c. What would be the time that the PM would be 30% confident of finishing by?
d. Explain the statistical principles that underpin the calculations in the first 3 parts.

Question 4

Using the final network analysis derived in question 3 :-

a. Construct a Gantt chart using Microsoft Project.
b. On the chart indicate the free and total float and demonstrate the new total duration
c. On a separate chart the progress bars as of 14 weeks if everything was on schedule (you may approximate to the nearest 25%).

Question 5

Due to the scale of this project and the potentially large numbers of stakeholders involved, identify stakeholders that are likely to have an impact on the project. Using suitable stakeholder management techniques, appraise the considerations of these stakeholders and derive a suitable stakeholder management strategy.

Harvard Referencing method.

Reference no: EM133566716

Questions Cloud

Destroy in pursuit of that great sound system : How much value did you destroy in pursuit of that great sound system and your free coffee mug. how much are you overpaying each month
Discuss aspects of a case formulation for psychodynamic : discuss aspects of a case formulation for Psychodynamic Psychotherapy using wheeler and knight case formulation and psychodynamic therapy algorithm
Identify relevant and reliable sources of data would consult : Identify and cite at least three relevant and reliable sources of data an epidemiological manager would consult when managing this outbreak.
Explain the od practitioner role in the process of entering : Explain the OD practitioner's role in the process of entering the organization and respecting the existing culture while concurrently recommending improvements
Construct a gantt chart using microsoft project : NG4S704 Project Management Theory and Practice, University of south wales - Critically deploy strategies in planning, designing, managing and executing
Analyze the factors that affect children school success : Analyze the factors that affect children's school success. Explain the influence of the individual child's characteristics (i.e., including personality
Analyze three different types of childrens vaccinations : Analyze three different types of children's vaccinations in terms of the economic cost to the United States.
How does this chapter challenge existing ideas or assumption : Were they new or in opposition to current views on the topic? What do you already know about the topic? Where did existing knowledge come from?
Consider project to produce solar water heaters : Consider a project to produce solar water heaters. which reflects the project's business risk.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd