Computing variance at completion for project

Assignment Help Project Management
Reference no: EM1335838

1. A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?

A. Impossible to know-not enough information
B. $112,500
C. $637,500
D. $750,000

2. Linda is a project manager for a large insurance company. Her current project is to organize all of the paper files to match the electronic structure of the IT system's servers. It is not an exciting project. Linda has just completed a performance report for her project. Her cost of performance index (CPI) is listed as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with a change request. Why?

A. The project is not performing well, so a change request is submitted to the project manager
B. The project is not performing well, so a change request is made to cancel the project
C. The project is not performing well, so Joey will likely issue a change request to remove Linda
from the project
D. The project is performing well, so Joey will likely be adding requirements to the project scope.

Reference no: EM1335838

Questions Cloud

Explain marketing core strategy : Explain Marketing Core Strategy and Provide a quick overview of the product or service you created you should continue using the content from the U3 Discussion Board
Hotel manage information as an asset : Explain How does a hotel manage information as an asset and Assess the effectiveness of the different methods
Juvenile probation officer : Job description for a juvenile probation officer Include a description of required job duties, as well as how probation fits into the juvenile justice system in general.
Common discretionary and contingent assessment methods : Find the  imilarities and differences between the  common discretionary and contingent assessment methods
Computing variance at completion for project : A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?
What value does a performance management program : Explain What value does a performance management program bring to the organization and Which performance management programs did you consider
Measuring verbal and computational skills : Measuring verbal and computational skills  to a group of applicants for a specific job.
Direct and indirect costs : Fee Setting - As the executive director of Advocates for Children, you have had a change of heart - perform all the computations necessary to set a fee. What will your fee be?
Define problem with criteria range : problem with criteria range. I do not know how to set two different criterias in one column. I need to ADVANCE FILTER all of the Clerks (1 and 2) and the Sect. 1 workers who create more than $5.50/hr. I do not understand how to set the title crite..

Reviews

Write a Review

Project Management Questions & Answers

  Result of repossession

On May 18, of last year, Carter sells unlisted stock with a cost of $24,000 for $60,000. Carter collects $20,000 initially and is scheduled to receive $10,000 each year for four years starting this year plus an acceptable rate of interest.

  Major erp systems from different erp software

Create a 7-10 slide presentation comparing and contrasting two major ERP systems from different ERP software providers.

  New product development

You are required to submit a written assignment relating to New Product Development.

  Explaining standard project scheduling technique

What are the implications of this regarding usage of any standard project scheduling technique?

  Functional organization verses a pure project environment

You have been assigned to a new and important project for your company. How would your management style differ if your project was being done in a functional organization verses a pure project environment?

  Basic service blueprint for ebags current product line

Develop a basic service blueprint for eBAGS' current product line. After analyzing your blueprint, would you recommend to eBAGS managers that they consider business process reengineering?

  Important information to create a project organization chart

What information is most and least useful to a project leader when creating a project organization chart?

  Project managers facilitate procurement

How can project managers facilitate procurement?

  Discuss five uses of a wbs in project management

The Work Breakdown Structure (WBS) subdivides the scope of work into manageable work packages that can be reliably estimated and assigned to a responsible person for completion. Discuss five uses of a WBS in Project Management

  Primary focus of the functional manager

What is the primary focus of the functional manager? Would you recommend this type of management for a project?

  Distribution strategy and project management

Distribution strategy and project management

  Protection to intellectual property

Compare and contrast the protection to intellectual property provided by trade secrets relative to that provided by patents.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd