Q1) Activity Immediate Predecessor Time (Week)

A none 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7

A. Draw the Network

B. What is the critical path?

C. How many weeks will it take to complete the project?

D. How much slack does activity B have?

Reference no: EM1339757

Questions Cloud

Explain maximizing shareholder wealth and payment of bribes : Explain Maximizing shareholder wealth and payment of bribes and Is there a conflict between maximizing shareholder wealth and never paying bribes when doing business abroad
Describe why the us farm policy is failing : Describe why the US farm policy is failing. Why were the WTO 2005-6 meetings a failure. What were the main issues and reasons.
Qualified plans : Find the  qualified plans for  Thomas to establish.
Find out an ideogram of human chromosome : Explain in words the nature of the woman's chromosome 1 abnormality.find out an ideogram of human chromosome.
Computing number of weeks take to complete the project : What is the critical path? How many weeks will it take to complete the project?
Explain legal critical thinking exercise : Explain Legal Critical Thinking Exercise and discuss the type of sexual harassment Mary thinks she is experiencing
Establishing the third amendment : In this posting, students will understand why the Third Amendment was established and how it protects American citizens against abuses of power by the government.
Plan permitting : Considering Rachel has never taken a plan loan before, determine the maximum loan Rachel can take, plan permitting?
Explain legal matters concern for public administrators : Explain Legal Matters concern for Public Administrators and Why have legal matters become such a concern for public administrators

Reviews

Write a Review

Project Management Questions & Answers

  Boundary conditions scope-time and cost

Why is it important to understand the boundary conditions "scope, time, and cost"of any information systems project.

  Evaluate the use of complex models of project risk

Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.

  Computing the coefficients of variation of project

Which of the following four projects should Mountain Ski Corp. choose? Compute the coefficients of variation to help you make your decision.

  Individual capital balances of remaining partners

After the withdrawal, what are the individual capital balances of the remaining partners?

  Importance of incorporating a budget into project schedule

Explain the importance of incorporating a budget into a project schedule.

  Computer production planning by linear programming

Help the computer manufacturer formulate and solve a linear programming spreadsheet model to find the production schedule that minimizes total cost over the given planning horizon.

  Possible steps included in project closure

What are possible steps included in project closure?

  Determining early and late start and finish times

Determine the early and late start and finish times and the slack times for the activities. Identify the critical path.

  Create weeklong work schedule to meet needs of employee

Create a weeklong work schedule to meet the needs of the employees, the customers, and therestaurant.

  Operating cash flow for project -straight-line depreciation

The company uses straight-line depreciation to a zero book value over the life of the project. The tax rate is 35%.

  Discuss five uses of a wbs in project management

The Work Breakdown Structure (WBS) subdivides the scope of work into manageable work packages that can be reliably estimated and assigned to a responsible person for completion. Discuss five uses of a WBS in Project Management

  Finding a forecasting model

Find a forecasting model that best answers MI Inc.'s questions. What is the forecast for each quarter in the next two years?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd