The following data are available for two mutually exclusive projects:(a) Compute the benefit-cost ratios for both projects.
(b) Compute the modified benefit-cost ratios for both projects.
Project A
Project B
PW(benefits)
$17,000,000
$15,000,000
PW(Operating and maintenance cost)
5,000,000
8,000,000
PW(capital cost)
6,000,000
3,000,000
(c) Compute the benefit-cost ratio for the increment between the projects.
(d) Compute the present worths of the two projects.
(e) \A nich is the preferred project? Explain.
When preparing a research report, where should you begin? Why?- List the various sections that go into making a marketing research report and briefly state what each section includes.
Explain a situation in which a project was not clearly aligned with business goals and was the project successful
What is the expected time to complete a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days, respectively?
In 1999, the world population was 6.0 billion and increasing at 1.3% per year; in 2009, it was 6.8 billion and increasing at 1.2% per year. In which year, 1999 or 2009, was dQ/dt (the rate of growth of Q with respect to t) greater? Explain.
Find the latest quotes for the euro, pound, and yen. By how much did these currencies rise or fall against the dollar in the last day?
1. why does the proper operation strategy keep changing for companies that are world-class competitors?2. what recent
Project Management solution - Explain what are some implications of completing a project before the scheduled completion date
Evaluate the scheduled completion time and identify the critical path and what is the slack time (float) for activities A, D, E, and G
change in value of the company if it accepts the replacement projectxyz manufacturing corporation currently has
What is the single most important task for users on a systems development project? Do you agree? Why or why not? Why must requirements emerge as a result of a conversation between users and IT professionals?
Using the Gap Model, identify the service gaps you noticed in your local grocery store. How might the store close those gaps?
Emphasize the importance of identifying critical path on projects and the manner in which one would allocate resources to all of the activities on the critical path.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd