Q12.12

Sid Davidson is the personnel director of Babson and Willcount, a company that specializes in consulting and research. One of the training programs that Sid is considering for the middle-level managers of Babson and Willcount is leadership training. Sid has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities and immediate predecessors appear in the following table:

Activity

Immediate Predecessors

A

--

B

--

C

--

D

B

E

A,D

F

C

G

E,F

Develop a network for this problem.

Q12.13

Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and the critical path. The activity times appear in the following table (see Problem 12.12):

Activity

Time (Days)

A

2

B

5

C

1

D

10

E

3

F

6

G

8

 

35

Q12.16

Monohan Machinery specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. George Monohan, president of Monohan Machinery, is convinced that harvesting weeds is far better than using chemicals to kill weeds. Chemicals cause pollution, and the weeds seem to grow faster after chemicals have been used. George is contemplating the construction of a machine that would harvest weeds on narrow rivers and waterways. The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the following table. Construct a network for these activities.

Activity

Immediate Predecessors

A

--

B

--

C

A

D

A

E

B

F

B

G

C,E

H

D,F

Q12.17

After consulting with Butch Rander, George Monhan was able to determine the activity times for constructing the weed-harvesting machine to be used on narrow rivers. George would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. (See Problem 12-16 for details). The activity times are shown in the following table:

 

Activity

Time (Weeks)

A

6

B

5

C

3

D

2

E

4

F

6

G

10

H

7

Q13.24

Bowman Builders manufactures steel storage sheds for commercial use. Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build an experimental model and related data are given in the accompanying table.

(a).        What is the project completion date?

(b).       Formulate an LP problem to crash this project to 10 weeks.(a).   

 

Activity

Normal Time

Crash Time

Normal Cost ($)

Crash Cost ($)

Immediate Predecessors

A

3

2

1,000

1,600

-

B

2

1

2,000

2,700

-

C

1

1

300

300

-

D

7

3

1,300

1,600

A

E

6

3

850

1,000

B

F

2

1

4,000

5,000

C

G

4

2

1,500

2,000

D,E

 

 

Reference no: EM13321848

Questions Cloud

Create a self-designed portfolio of four common stocks : Create a self-designed portfolio of four common stocks selected from the NASDAQ or NYSE stock exchanges. Assume the weighting of the portfolio to be 15%, 30%, 35%, 20%. Explain how to calculate the standard deviation for each stock in your portfolio ..
Secular humanists feel : Secular Humanists feel that, "The good is not what some abstract God dictates, but what contributes to the liberation, growth, and progress of human beings. Instead of being God-centered, we should be human-centered". What do you think about this sta..
Active union members : Active union members often have two jobs to do--as an employee and as a union member. How far do you think an emplohyer should be required to go t allow the member to do both jobs?
Root cause and improving the manufacturing process : Quality Textiles International is an organization that weaves fabric and then prepares the required sheet lengths as desired by customers. Based on your data analysis, what assumptions and recommendations would you make for getting at root cause and ..
Cb2201 quantitative methods solutions manual : CB2201 Quantitative Methods Topic 5: Project Management (Questions), Sid Davidson is the personnel director of Babson and Willcount, a company that specializes in consulting and research. One of the training programs that Sid is considering for the m..
Measures stress-executives have a dangerous level of stress : A researcher is using a questionnaire that measures stress. The questionnaire has been vallidated through past use. A score above 80 indicates stress at a dangerous level. A random sample of 15 executives revealed the following stress level scores. 9..
Computer scientist has designed a remarkable machine : A certain computer scientist has designed a remarkable machine which gives a correct answer to any yes no question typed into it via its keyboard. The machine answers by flashing a blue or a yellow light, one of the colors signifing "yes", the other ..
Markup calculation : Use the following data to calculate the relevant markup on cost and markup on price: product price marginal cost markup cost% markup price%
What is one important distinction-boston tea party : What is one important distinction you could not overlook making when critically evaluating the information provided in these materials about the Boston Tea Party? Clarify the importance of that distinction.

Reviews

Write a Review

Project Management Questions & Answers

  Characteristics of an effective project manager

Out of the eight traits associated with being an effective project manager, choose three that you possess and how do these traits contribute to effectively managing the execution of a project

  Important issue facing private security

What do you believe the most important issue facing private security today is?

  Importance of introversion as a good quality

In the Big Five personality factors, extroversion is considered a good quality to have and why might introversion be an equally positive quality?

  What are ways to encourage meeting participation

List four methods used for the distribution of end-of-meeting reports to senior management or CEO and list four reasons for reporting end-of- meeting outcomes to senior management within a specific timeline.

  Formulate as a linear programming problem

The standard unit requires 60 minutes, while the deluxe requires 120. Formulate as a linear programming problem, and solve using the corner points solution method.

  Evaluate technical performance

Can the project manager effectively deteremine the functional employee on technical performance? If not, then on what information can the project manager base his evaluation?

  Types of risks are inherent in a project

What types of risks are inherent in a project? Where do they originate? Can they be mitigated? How? What are the consequences of ignoring a conflict within a project team?

  Communication barriers to effective communication

which communication barriers do you need to be concerned with and address in order to effectively communicate your message?

  Make a targeted cover letter

Prepare a paragraph that explains the correlation you found between the job ad and the information on the organization's site.

  What is the difference between negligence and strict

What is the difference between negligence and strict liability? What are some of the latest amendments to the Truth-in-Lending Act?

  What was salems expected net present value for this project

Present value information is given below so what was Salem's expected net present value for this project

  What are leadership styles

The secret to being a successful manager is to use good communication skills that create a positive image. What are three leadership styles?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd