ASSIGNMENT
Project Management
Directions: Sources must be cited in APA format. Refer to the "Assignment Format" page for specific format requirements.
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project.
Can the project be completed in 40 weeks?
Assume that Activity A actually finished at 3 weeks, Activity B actually finished at 12 weeks, and Activity C actually finished at 13 weeks.
Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?

Write in 4 pages double spaced APA with Times roman 12 font with reference.
The ebook is provided in the attached.
Format Requirements
Use the following format requirements on all submissions.
•Writing Style APA (American Psychological Association)
Note: To find detailed information on APA manuscript style guidelines on the Internet, go to www.apastyle.org.
•Margins 1" all sides
•Paragraphs The entire document should be double-spaced on standard-sized paper (8.5" x 11")
•Headings Bold
•Type Style and Size Times New Roman, 12 point
•Software MS Word
Attachment:- Successful-Project-Management-Chapter-5-Developing-the-schedule.pdf
How do we know if it is achieving diseconomies of scale
: What must AutoEdge do," he says, "to obtain economies of scale with production? How do we know that it has achieved economies of scale? Conversely, how do we know if it is achieving diseconomies of scale?
|
Ewxplain two strategies that hershey is actually pursuing
: Determine two strategies that Hershey is actually pursuing. Give some pros and cons of those two new Hershey strategies.
|
Write an essay on free market or protectionism
: Other issues are involved in the economy that it will be mentioned as well. Opening the market and a minimal intervention of the government will help to create a better environment for the economy. Write an essay on Free Market or Protectionism: A..
|
Demonstrate personal passion for your position
: Demonstrate personal passion for your position and critical thinking with persuasive language, sound logic, valid claims, and credible support for the claims.
|
Can the project be completed in 40 weeks
: Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project.
|
What is the expected profit
: 1. Suppose an investment has three possible outcomes. There is a 50% chance that it brings a profit of 4,000,000. There is a 40% chance that it brings a profit of 1,000,000. There is a 10% chance that is brings a profit of 0. What is the expec..
|
Calculate the electric field intensity
: Point charges above a conducting plane. Two charges are located above a conducting plane as shown in Figure 5.35. Calculate the electric field intensity
|
Which stage of the product life cycle is the dvd today
: In the 1990s, DVDs replaced audiocassettes and floppy disks as the storage media of choice for music and computers. At which stage of the product life cycle is the DVD today?
|
Incentives of government bureaucrats
: What are the incentives of government bureaucrats who run public services such as the water services, the parking services, and the airports? Do these incentives differ from those of private companies in running these services? Why or why not?
|