Q1) Given this information about an activity: ES = 10, EF = 15, LS = 26, and LF = 31. The amount of slack associated with the activity is?

Q2) Using the following project information, calculate the variance for each of the project activities.

Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s)
A 3 6 9 none
B 3 5 7 A
C 4 7 12 A
D 4 8 10 B
E 5 10 16 C
F 3 4 5 D,E
G 3 6 8 D,E
H 5 6 10 F
I 5 8 11 G
J 3 3 3 H,I

Reference no: EM1336942

Questions Cloud

Calculating completion time for the project : Calculate the completion time for the project. (Completion time = weeks)
Computing unlevered beta : Morgan Entertainment has a levered beta of 1.20. The firm's capital structure consists of 40% debt and 60% equity-Find out Morgans's unlevered beta?
What is the best way to write down the value ''7564'' : What is the best process to write the value '7564' and make it clear to the reader that the number should be interpreted as a hexadecimal value?
Discuss what has occurred to change the demand : Assume the basis for the trends in consumption patterns as discussed in the article. Discuss what has occurred to change the demand for, or the supply.
Calculating variance for the project activities : Using the following project information, calculate the variance for each of the project activities.
Explain how do you calculate the expected intrinsic value : Explain How do you calculate the expected intrinsic value of the stock for Xavier Company
Optimal capital structure for time warner : Discuss the optimal capital structure for Time Warner in light of current, business, economic, and industry trends.
What information is define by multiplicity on an association : What information is shown by multiplicity on an association end. I want to provide an example demonstrating my explanation that does not come from the ATM example.
Steve jobs leadership : How has Apple Computers, under Steve Jobs' leadership, managed to become a major world company, since 1997 (10 years)?

Reviews

Write a Review

Project Management Questions & Answers

  Determining the annual net cash flows

If the firm is in the 40 percent marginal tax bracket, determine the annual net cash flows generated by the drill press.

  What do you realize by term trade-off

What do you realize by term "trade-off"

  Calculating company-s profit at each level of production

Calculate company's profit at each level of production. Assume that the company will sell all of its output. At what production level is profit maximized?

  Talk about fragmentary identities

Social psychologists and even sociologists a lot of times talk about fragmentary identities that exist in people bicultural people.

  Stakeholders and accounting ethics

Mike Singletary, president of Singletary industries, wishes to issue a press release to bolster his company's image and maybe even its stock price which has been gradually falling. Who are the stakeholders in this situation?

  Determining the net operating cash flow

There is a variable operating cost that is 60% of sales and the company's marginal tax rate is 35%. Determine the net operating cash flow for Years 1, 2, and 3.

  Advantages and disadvantages of inspection

What are the advantages and disadvantages of workers having more control over the inspection of their own work?

  Projects include risk in project planning

Why should all projects include risk in their project planning? What are some of the drawbacks if risks are not considered?

  Risk identification with project contingency planning

How does risk identification help with project contingency planning?

  Determining number of agent at ticket counter

Simulate this model and determine the number of agents needed to achieve an average waiting time of 5 minutes or less. This will require an iterative approach in which you run the model with one server, then with two servers, three servers and so ..

  Stakeholders not communicate politely as project leader want

Stakeholders may not communicate as frequently or politely as a project leader prefers.

  Process of doing a system of inquiry

Describe the process of doing a system of inquiry for codes of ethics. Make a system of inquiry to be employed in evaluating decision-making, problem solving, and behavior in the business setting.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd