Q1) The progress report of a project contains the following data about the project costs:

BCWS = $ 46,500
BCWP = $ 49,200
ACWP = $ 54,250
BAC = $ 183,600

a.) Calculate CV

b.) Calculate CVP

c.) Calculate CPI

d.) Calculate SV

e.) Calculate SVP

f.) Calculate SPI

g.) Calculate EAC

h.) Calculate VAC

i.) Comment on the way the project is progressing.

Reference no: EM1336967

Questions Cloud

Secondary data sources : Discuss the problems while using secondary data sources.
Explain how could you use the concepts of marginal cost : Explain how could you use the concepts of marginal cost and marginal revenue to maximize profit? What information do you need to determine this.
Capital structure-stephens security : Stephens Security has two financing alternatives: (1) A publicly placed $50 million bond issue. Which alternative has the lower cost (annual percentage yield)?
Explain public relations campaign overview : Explain Public relations campaign overview and We are creating a PR campaign overview for the introduction of a new COKE product
Calculating vac-cpi-svp and eac of project : The progress report of a project contains the following data about the project costs:BCWS = $ 46,500. Calculate SPI, EAC and VAC.
Assume f is a function : assume f is a function that returns the result of reversing the string of symbols given as its input, and g is a function that returns the concatenation of the two strings given as its input. If x is the string abcd, what is returned by g(f(x),x).
Relate to the previous task also define for both examples : Relate to the previous task also define for both examples the current market situation - Surplus or Shortage.
Evalutate capital structure of clorox company : This problem asks you to measure the capital structure policies of The Clorox Company as of fiscal year-end 2007. Your aim will be to decide whether Clorox's use of debt financing is proper or whether, given the company's circumstances, it may pru..
Common law and statutory law : Describe the difference between common law and statutory law. Where does each type derive from?

Reviews

Write a Review

 

Project Management Questions & Answers

  Prepare a monthly profit report

Prepare a "Monthly Profit Report", Create this report using the results of your ABC overhead allocation.

  What do you understand by net present value

You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue

  Completion time for project if duration of activity is given

What is the revised completion time for the project if duration of activity E is 3 weeks?

  Define a project and describe its characteristics

Define a project and describe its characteristics and What are the necessary competencies and skills of a project Manager?

  Expected time to complete a task with optimistic times

What is the expected time to complete a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days, respectively?

  Explaining standard project scheduling technique

What are the implications of this regarding usage of any standard project scheduling technique?

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  List key stages of a typical procurement cycle

List key stages of a typical procurement cycle

  Enhancing steps associated with reengineering

Select the PERT technique you consider LEAST valuable when altering or enhancing steps associated with reengineering. Explain your choice. Describe and analyze how the two techniques you chose influence the Critical Path Method.

  Describing the purpose of attributes of a project

Using the concepts within the textbook "A Not-for-Profit Organization" , outline some attributes of a project, and describe their overall purpose.

  Definition of quality dimensions

Provide an example of a "best buy" from your professional experience where quality aspects were not met in accordance to the text definition of quality dimensions.

  Projects include risk in project planning

Why should all projects include risk in their project planning? What are some of the drawbacks if risks are not considered?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd