Calculate the npv and irr of each project

Assignment Help Project Management
Reference no: EM13232097

A company is considering which of two mutually exclusive projects should be undertaken. The Finance Director suggested that the project with the higher NPV should be chosen whereas the Managing Director suggested that the one with the higher IRR should be undertaken. Both projects have the same initial investment and length of life. The company anticipates a Discounting Factor of 10% and future cash flows of the projects are as follows:

Year

Project A

Cash flow

Project B

Cash flow

Investment

-200,000

-200,000

1

35,000

218,000

2

80,000

10,000

3

90,000

10,000

4

75,000

4,000

5

20,000

3,000

You are required to:

i. Calculate the NPV and IRR of each project.

ii. Recommend, with reasons, which project you would undertake (if either).

Reference no: EM13232097

Questions Cloud

Explain half reaction for the deposition of silver : A constant electric current deposits 0.365 g of silver metal in 12960 seconds from a solution of silver nitrate. What is the current? What is the half reaction for the deposition of silver. Molar mass of Ag is 107.
Contrast case studies with ethnographic research : What benefits can be gained from case studies? What dangers, if any, are there in using case studies? In what ways are they useful? Support your answers.
Write a pseudocode statement : Write a pseudocode statement that subtracts the variable downPayment from the variable total and assigns the result to the variable due. Don't use integer as decimal places will be needed.
Compare the treatment of mental illness in the medical model : Compare the treatment of mental illness in the medical model, the public health model, and the human service model. Which model provides the best treatment or approach in your opinion? Why?
Calculate the npv and irr of each project : Calculate the NPV and IRR of each project and recommend, with reasons, which project you would undertake (if either).
What makes an efficient internal hazard reporting : What makes an efficient internal hazard reporting and distribution system? Where are the possible failures in sustaining these in-house programs?
What are the parameters and the potential implications : What are your thoughts on this? What are the parameters and the potential implications for failure to adhere to those parameters?
Explain what is the concentraction of 2 phosphoglycerate : The value of Delta g for the conversion of 3-phosphoglycerate to 2-phosphoglycerate (2PG) is +4.4 kj/mol. If the concentration of 3-phosphoglycerate at equilibrium is 2.55 mM, what is the concentraction of 2 phosphoglycerate? assume a temperature ..
Determine what believe the top-five challenges integrating : Autonomous vehicles utilize integrated imaging and vision systems, sensor systems, and control systems to "drive a car". Determine what you believe are the top-five challenges of integrating these systems

Reviews

Write a Review

Project Management Questions & Answers

  Progress reports an integral part of project communications

Explain why are progress reports an integral part of project communications and what should they include

  Project management affect success of project outcome

The benefits of project planning, project management within the various types of organizational systems, and how your approach to project management will affect the success of the project outcome.

  Differentiatingtask from project

What differentiates a Task from a Project? What is your understanding of Managing as suppose to Directing a Project?

  Future of integrated business communication

Address what role technology will play in the communication of thoughts and ideas and show how the information gap between generations, cultures, income levels, and education can be resolved.

  Explain how can i include costs

Setting up costs in Microsoft Project 2000 for project management -  Explain how can I include costs?

  Communication plan - barriers presentation

Communication Plan - Barriers Presentation - Prepare a Microsoft PowerPoint presentation

  Develop maut model and ahp model

Develop a MAUT model to assist in the selection process. Develop an AHP model to assist in the selection process.

  Project management software help it project to achieve goal

Include a discussion of how project management software can help IT project managers achieve their goals.

  Explain the six methods for estimating task duration

Explain the six methods for estimating task duration and show how each method affects the accuracy of task duration estimates.

  Would you recommend that this project be adopted

Fortran Corporation - Would you recommend that the project be adopted

  Calculating every contingency cost

Should you, as the project manager, try to control and calculate every contingency cost you can think of?

  Stakeholders and accounting ethics

Mike Singletary, president of Singletary industries, wishes to issue a press release to bolster his company's image and maybe even its stock price which has been gradually falling. Who are the stakeholders in this situation?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd