Calculate the earliest start and finish times

Assignment Help Project Management
Reference no: EM13211070

1. Based on the data below:

(a) Draw a network diagram for the project, highlight the  "normal" critical path

(b) Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations

(c)  If indirect costs of £375 per day could be saved by reducing the overall duration of the project,  what is the minimum cost for the project?

(d) What practical factors should be considered before an activity is crashed?

(e) Describe a practical approach to monitoring the progress of a project like this one.

Activity

Preceded by

Normal days

Crash days

Normal cost (£)

Crash Cost (£)

A

-

4

3

800

900

B

-

6

3

1000

1600

C

-

4

3

900

1200

D

A

5

3

700

1200

E

B,C

4

3

600

750

F

D,E

3

3

400

400

G

F

4

3

800

850

H

F

8

3

1200

3200

I

G,H

9

3

1200

3300

J

H

3

3

600

600

K

J

5

3

2000

2800

L

I,K

7

3

6500

5000

2. Based on the data below calculate the probability that the project will be completed in 20 days or less and discuss the practical considerations that would be relevant if a company doing this project faced a penalty for completion in more than 20 days. What action could be taken to improve the chances of completion within a  20 day period?

Activity

Preceded by

Optimistic days

Most likely days

Pessimistic days

A

-

2

3

4

B

-

4

6

8

C

A,B

6

9

12

D

A,B

4

5

12

E

C,D

3

5

7

Reference no: EM13211070

Questions Cloud

Explain vessel of fixed volume and at a temperature : The two phases are allowed to come to equilibrium with their product ammonia in a vessel of fixed volume and at a temperature
State the equivalence volume ve of the titration in ml : consider the titration of 25.00ml of 0.650 M propanoic acid, HC3H5O2 ( Ka = 1.3 X 10^-5), with 0.750 M sodium hydroxide, NaOH, and answer the following questions?
Find out the minimum concentration of koh required : Potassium hydroxide is used to precipitate each of the cations from their respective solution. Determine the minimum concentration of KOH required for precipitation to begin in each case.
Explain herbigon is dissolved in 1 m acetic acid : As a chemist for an agricultural products company, you have just developed a new herbicide,"Herbigon," that you think has the potential to kill weeds effectively
Calculate the earliest start and finish times : Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations and draw a network diagram for the project
Explain the ph change of solution of citric acid : What is the pH change of a 0.200M solution of citric acid (pKa=4.77) if citrate is added to a concentration of 0.175M with no change in volume?
What is the effect of temperature on compressive strength : what is the effect of temperature on compressive strength of concrete?
Build a balanced scorecard for the unit of the organization : Build a Balanced Scorecard for the unit of the organization for which you work, or have worked. Unless you are in senior management, focus on the unit with which you are most familiar rather than the organization as a whole
Explain alcohols generally require acid catalyst : Alcohols generally require acid catalyst in order to undergo substitution by nucleophiles. The acid catalyst enhances the reaction by

Reviews

Write a Review

Project Management Questions & Answers

  Resource constrained

How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule?

  Draw a project network from given information

Activities b and h can be shortened to a minimum of 2 weeks and which activity would you shorten to reduce the project duration by 2 weeks

  Provide an example from an organization

Communication and Trust - Provide an example from an organization of a situation that created or destroyed trust and highlighted some of the consequences.

  Create estimates in regards to pm are

Describe to me what the disadvantages as well as the advantages of using spreadsheets to create estimates in regards to PM are?

  Skills for a successful project manager

Write an essay that explains and discusses the skills to be a successful project manager

  Show the project management question

What should be your competitive priorities and what capabilities do you want to develop in your own core and support processes?

  What could you do to overcome this potentially confounding

What could you do to overcome this potentially confounding factor in accuarately determining information requirements?

  What is the minimum number of service bays fast lube needs

what is the minimum number of service bays fast lube needs to achieve an anticipated production of 300 cars per 8 hour day?

  Measurements of leadership emotional intelligence

One of the measurements of leadership is the EQ (Emotional Intelligence) score. Anthony Mersino attempts to show the place of EQ with the project manager and states Emotional Intelligence is vital to Project Managers.

  Project management - systems development

Project Management - Which project management methodology would you choose to run your software development project?

  When does delivery formally arise

When does delivery formally arise

  Benefits of dealing with a national labor market

What are some benefits of dealing with a national labor market and what are some risks? Should a business ever avoid dealing with a national labor market? What would be an example?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd