1. Based on the data below:
(a) Draw a network diagram for the project, highlight the "normal" critical path
(b) Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations
(c) If indirect costs of £375 per day could be saved by reducing the overall duration of the project, what is the minimum cost for the project?
(d) What practical factors should be considered before an activity is crashed?
(e) Describe a practical approach to monitoring the progress of a project like this one.
Activity
Preceded by
Normal days
Crash days
Normal cost (£)
Crash Cost (£)
A
-
4
3
800
900
B
6
1000
1600
C
1200
D
5
700
E
B,C
600
750
F
D,E
400
G
850
H
8
3200
I
G,H
9
3300
J
K
2000
2800
L
I,K
7
6500
5000
2. Based on the data below calculate the probability that the project will be completed in 20 days or less and discuss the practical considerations that would be relevant if a company doing this project faced a penalty for completion in more than 20 days. What action could be taken to improve the chances of completion within a 20 day period?
Optimistic days
Most likely days
Pessimistic days
2
A,B
12
C,D
How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule?
Activities b and h can be shortened to a minimum of 2 weeks and which activity would you shorten to reduce the project duration by 2 weeks
Communication and Trust - Provide an example from an organization of a situation that created or destroyed trust and highlighted some of the consequences.
Describe to me what the disadvantages as well as the advantages of using spreadsheets to create estimates in regards to PM are?
Write an essay that explains and discusses the skills to be a successful project manager
What should be your competitive priorities and what capabilities do you want to develop in your own core and support processes?
What could you do to overcome this potentially confounding factor in accuarately determining information requirements?
what is the minimum number of service bays fast lube needs to achieve an anticipated production of 300 cars per 8 hour day?
One of the measurements of leadership is the EQ (Emotional Intelligence) score. Anthony Mersino attempts to show the place of EQ with the project manager and states Emotional Intelligence is vital to Project Managers.
Project Management - Which project management methodology would you choose to run your software development project?
When does delivery formally arise
What are some benefits of dealing with a national labor market and what are some risks? Should a business ever avoid dealing with a national labor market? What would be an example?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd