Calculate earned value measures for each activity

Assignment Help Project Management
Reference no: EM131899838

Project Management Assignment -

Introduction - All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results.

In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT.

Problem Background - Your project consists of seven activities with planned start and finish dates shown in the chart below:

1603_figure.png

Activity budgets and earned value (EV) accrual rules from you project cost management plan are as follows:

Activity

Budget

EV Accrual Rule

1

25,000

Percent Complete with Gates

2

20,000

Fixed Formula - 0/100

3

50,000

Weighted Milestones

4

60,000

Percent Compete with Gates

5

30,000

Fixed Formula - 40/60

6

20,000

Fixed Formula - 30/70

7

10,000

Fixed Formula - 100/0

Assumptions -

1. Assume a five-day work week with no holidays occurring during the work week.

2. For all activities (except activities 3 and 4), assume the expenditure rate is constant over the duration of the activity, i.e., the amount planned to be spent each week is the same. See the conceptual profile below.

1081_figure1.png

3. For activity 3, the planned expenditure profile is shown below:

744_figure2.png

4. For activity 4, the planned expenditure profile is shown below:

1453_figure3.png

The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through the end of week 8. You have collected the following information:

Activity

Actual Start

Actual Finish

Expended

1

Start of week 1

End of week 5

22,000

2

Start of week 6

End of week 8

25,000

3

Start of week 3

 

40,000

4

Start of week 8

 

8,000

5

 

 

0

6

 

 

0

7

 

 

0

For activity 1, three equally-valued gates have been established and all gates are complete as of the end of week 8.

For activity 3, five milestones have been established with the following values: (1) milestone 1 - 10%; milestone - 20%; milestone 3 - 15%; milestone 4 -20%; milestone 5 - 35%. Four of the milestones are complete as of the end of week 8.

For activity 4, four equally values gates (milestones) have been established. As of the end of week 8, none of the gates have been reached but the activity owner estimates 30% of the work required to reach the first gate has been accomplished.

1. Earned Value Measures

a. Calculate earned value measures for each activity and for the cumulative project as of the end of week 8;

2. Earned Value Performance Measures

a. Calculate earned value performance parameters for each activity and for the cumulative project as of the end of week 8;

b. Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?

c. Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why?

3. Earned Value Forecasts

a. What is the value of the "Cumulative CPI" Estimate-at-Completion (EAC)?

b. Using the "Mathematical" or "Overrun to Date" Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)?

c. Using the "Cumulative CPI times SPI" Estimate-At-Completion, how much more or less money (other than the current budgeted amount) will you need to finish the project?

d. How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?

Attachment:- Assignment File.rar

Reference no: EM131899838

Questions Cloud

Explain the legal positions of tullula investments : Explain the legal positions of Tullula Investments and Italian Cuisine in relation to the law of contract, covering such issues as contract formation,
What is the variable cost of losing : A warehouse with monthly demand of 146 units establishes an inventory policy with shortages planned by 4 units. The cost of making an order is $ 118.
What methods should each class have : What methods should each class have? How and where would you keep track of things like orbital parameters?
Find the present value of perpetuity : Find the present value of a perpetuity of $1,500 per year, given a 20% opportunity cost.
Calculate earned value measures for each activity : Earned Value Measures - Calculate earned value measures for each activity and for the cumulative project as of the end of week 8
Current price of a bond issued by dundee international : What is the current price of a bond issued by Dundee International which pays a semiannual coupon rate of 6 8/9%?
Operate as corporation rather than as sole proprietorship : Which of the following could explain why a business might choose to operate as a corporation rather than as a sole proprietorship or a partnership?
Determine the upper control line for a p-chart : You want to determine the upper control line for a p-chart for quality control purposes. You take several samples of a size of 100 items in your production.
Estimating cost of equity using capm : Estimating cost of equity using CAPM (SML) - FORD MOTOR (F)

Reviews

len1899838

3/13/2018 5:43:48 AM

Subject - Project Management Accounting, Topic - Project Management, Deadline - 14 12:0:00 and References - Ignore if not required. Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places. In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT.

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd