Calculate earned value for the first two weeks

Assignment Help Project Management
Reference no: EM133402535

You've volunteered to make bird houses, at your own expense and on your own time, to be offered for sale at your daughter's high school fair to raise money for new sports equipment. You have three different designs in mind. You estimate the first design will require about $5 in material cost and about two hours of work. The second design is a little more elaborate and will require about $10 in material cost and three hours of work. The last design, more elaborate yet, will require about $15 in material cost and four and a half hours of work.

There are about 5 weeks remaining until the school fair. You figure you can safely work an average of between 35 and 40 hours per week (week day nights and weekends) and you only have $600 available to complete the project. After doing some expected value calculations, you conclude the best product mix is 25 birdhouses using the first design, 20 birdhouses using the second design, and 15 birdhouses using the third design. You develop a construction plan as follows:

Calculate the planned budget for each week of the project and for the total project.

1. At the end of week 2, you look at your actual progress and find the following:

Calculate Earned Value for the first two weeks of the project and the project to-date.

Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?
2. Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why?

3. Assuming you continue working as you are without making any changes to your processes or materials, what is the forecast of total project cost? Will you exceed your total available funds?

4. Assuming you continue working as you are without making any changes to your processes or materials, what is the Variance at Completion (VAC)?

5. At the end of week 3 you discover you that SV is still positive but SPI is 0.95. What does this mean?

Reference no: EM133402535

Questions Cloud

What factors might drive you to decompose your wbs : How low do you go? What factors might drive you to decompose your WBS further? In this discussion thread, you should briefly describe one factor or reason
Who helps odysseus return to ithaca after twenty years : Who helps Odysseus return to Ithaca after twenty years? Once in Ithaca, whom does Odysseus visit and how is he disguised? In Odysseus' absence
Identify opportunities and set result-oriented aspirations : Use the SOAR analysis framework to identify opportunities and set result-oriented aspirations based on the strengths of Molson Coors Brewing Company.
What can a leader do to recognize and engage the strength : What can a leader do to recognize and engage the strength of others? 2. Which do you think is more important? Self-assessments or assessments by others? Why
Calculate earned value for the first two weeks : What EVM information are you using to make this assessment and why? 2. Is the project over budget, under budget, or on budget? What EVM information
Evaluate the sts method of random-digit dialing : Evaluate the geographic options offered by STS. Do they seem to cover all the bases - Evaluate the STS method of random-digit dialing
Define exactly what this wonderful thing is : define exactly what this "wonderful thing" is. Has Nora lost her mind, or can there really be such a thing (something that is both "wonderful" and "terrible"
Discuss how the concepts of procurement management help : Discuss how the concepts of procurement management help prepare you for a career in project management.
Calculate the expected duration of each activity : Calculate the expected duration of each activity and Calculate the expected duration and variance of the critical path.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd