Calculate Cost performance index and Schedule variance

Assignment Help Project Management
Reference no: EM132328612

Project Management Question:

Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?

PV = $25,000

EV = $30,000

AC = $29,000

BAC = $1,000,000

a. Schedule variance (SV)

b. Cost variance (CV)

c. Schedule performance index (SPI)

d. Cost performance index (CPI)

e. Estimate to complete (ETC-first method)

f. Estimate to complete (ETC-second method)

g. Estimate at completion (EAC)

h. To-complete performance index (TCPI).

Reference no: EM132328612

Questions Cloud

Description of key question that was addressed by authors : Provide a concise yet through description of the key question that was addressed by the authors, the authors did not address but should have,
What is the present value of the following annuities : What is the present value of the following annuities - 2,800 a year for 8 years discounted back to the present at 9 percent
Which project should Timco choose : Project Management - Finance Question: The cost of funds is 8%. Which project should Timco choose? Show the numbers to prove it
What is the value of the bond : If your required rate of return is 13 percent, what is the value of the bond? What is the value if the interest is paid annually
Calculate Cost performance index and Schedule variance : Calculate Cost performance index and Schedule variance. Describe what the results of each calculation mean to you as a project manager
What spot exchange should one forecast five year into future : If PPP is expected to hold between the two countries, what spot exchange should one forecast five years into the future
Demonstrate the effect of its environmentally : Use a graph of the market for possum fur to demonstrate the effect of its environmentally friendly status on the market equilibrium.
Promotion of ethical values the solution : Is positive discipline the solution? Is empowerment the solution? Is the promotion of ethical values the solution? Why, explain, example
Increase in income in situation : Which one of the following factors could have caused the increase in income in this situation?

Reviews

Write a Review

Project Management Questions & Answers

  Identify one component in the performance management process

Identify one component in the performance management process at the Balme Library that has not been implemented effectively?

  Analyze and explain the steps taken by the organization

Analyze and explain the steps taken by the organization to diversify their assets and integrate themselves into the growing global economy.

  Explain how project management has evolved

Explain how project management has evolved from 1945 to the present day - Provide one example of a major change in project management that occurred during this time period, and explain its significance.

  Graph t and on the same coordinate system

What is the point of diminishing returns and the maximum rate of change of baseball cap production? Graph T and on the same coordinate system.

  Use of strategic considerations to justify a project

Many financial analysts are very skeptical of the use of strategic considerations to justify a project.

  How does training differ from education

Which of the SETA program's three elements-education, training, and awareness-is the organization best prepared to provide itself?

  How do consumption habits for products

Why are Diageo, Pernod Ricard, and other marketers of global spirits brands localizing advertising campaigns in emerging markets?

  What are the disadvantages of inflating a project

Users will have both LAN and remote access to email. What are the disadvantages of inflating a project based on PERT estimating or incorporating risk?

  What effect did it have on the project

Risk is present in nearly every human undertaking and projects are no exception. Recall a project that you have participated in and name at least one risk that was recognized before it happened. What effect did it have on the project

  Discuss the project management life cycle with your ppm

Discuss the project management life cycle with your PPM software implementation project. Each life cycle element should have at least 2 major activities or tasks of the software implementation project.

  Ways to manage resources in integrated project management

Describe three ways to manage resources in integrated project management.

  Why is the visible involvement of senior

Why is the visible involvement of senior executives in post-project reviews essential?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd