Build out of the new facility

Assignment Help Project Management
Reference no: EM131375912

The Project Case under consideration have the following major Headings:

1. Project Planning

2. Pre-move Activities

3. Moving Activities

4. Post-move Activities

these could be denoted as the Major Tasks.

The tasks that have been identified are:(As Given)
- Decide on new furniture
- office preparation
- kick-off meeting
- set up utilities
- build out of the new facility
- initial planning for overall project
- actual move of existing furniture and files
- installation of new communication equipment, servers, and computers
- pack-out of existing office files, supplies, and material
- Installation of new signs
- Project closeout activities.

These could be denoted as the Sub-Tasks.
Some of the other main activities or tasks that needs to be completed are: (Some Preconditions)
- Relocate the entire office of 200 people to a new office building across town.
- Purchase and installation of items for the new building is part of the project's responsibility.
- Removal of items not being moved and general cleanup of the old office space is outside the scope of this project.
- Moving of all large, heavy items will be outsourced to a professional moving company.
- IT plans to replace all computers and servers with updated technology.
- The move is scheduled for the last week in July.

These could be denoted either as the Master or the sub-sub tasks as per the headings(Hans, 2013).

Some Assumptions:
- The work staring from 1st Feb, 2017
- No Holidays considered
- In a week it is considered to be 5 working days with holidays on Saturdays & Sundays.
- The work duration for each task is considered as per standard timings

However, after clubbing the above Major Tasks, Sub-Tasks, Master or the Sub-sub tasks the Project Schedule along with the WBS numberings could be done.

WBS Sl No

Project Work

Predecessors

Duration (Days)

Start Date

Finish Date

1

Relocate the entire office of 200 people to a new office building across town

 

 

 

 

1.1

Project Planning 

 

 

 

 

1.1.1

Initial planning for overall project

Start

 

 

 

1.1.2

Kick-off meeting

1.1.1

5 Days

1/2/2017

7/2/2017

1.2

Pre-move Activities 

 

 

 

 

1.2.1

Office preparation

1.1.2

10 Days

8/2/2017

21/2/2017

1.2.2

Decide on new furniture

1.2.1

10 Days

22/2/2017

7/3/2017

1.3

Moving Activities 

 

 

 

 

1.3.1

Professional Moving Company Deployed

 

 

 

 

1.3.1.1

Actual move of existing furniture and files

1.2.2

15 Days

8/3/2017

28/3/2017

1.3.1.2

Pack-out of existing office files, supplies, and material

1.3.1.1

15 Days

29/3/2017

18/4/2017

1.4

Post-move Activities 

 

 

 

 

1.4.1

Purchase and installation of items for the new building

 

 

 

 

1.4.1.1

Build out of the new facility

1.3.1.2

10 Days

19/4/2017

2/5/2017

1.4.1.2

Installation of new signs

1.4.1.1

5 Days

3/5/2017

9/5/2017

1.4.1.3

Set up utilities

1.4.1.2

10 Days

10/5/2017

23/5/2017

1.4.2

IT plans to replace all computers and servers with updated technology

 

 

 

 

1.4.2.1

Installation of new communication equipment, servers, and computers

1.4.1.3

15 Days

24/5/2017

13/6/2017

1.4.3

Project closeout activities

1.4.2.1

5 Days

14/6/2017

20/6/2017

Table: Project Schedule & WBS of the Project for relocation, Source: (Hillson, 2003)

Now that you have created the work breakdown structure and received approval to begin scheduling the office move, your manager, Steve Spaniels, would like to review a network diagram and present it to the CEO.

You have worked with your project team to estimate the durations of each of the work packages in the WBS. The following is your current plan:

Work Package

Duration (days)

Predecessors

1) Initial planning

20

 

2) Kick-off meeting

1

 

3) Decide on furniture

25

 

4) Office preparation

20

 

5) Actual move

5

 

6) Build out of new facility

45

 

7) Install of furniture/servers/equipment

10

 

8) Set up utilities

30

 

9) Pack-out existing office

10

 

10) Install new company signs

15

 

11) Closeout activities

5

 

Assignment:

Please review the Network Diagraming section in Chapter 6 of the text (starting on page 201). Create a project network diagram by first identifying the task predecessors (above). Once you have completed the network diagram:

1) Calculate the forward pass and backward pass

2) Calculate activity slack and project float

3) Identify critical path

Journals are private between the student and the instructor. Approach these activities as (a) an opportunity to reflect upon and apply what you learn each week based on the assigned readings, discussions, and activities, and (b) an opportunity to share your knowledge and expertise based on your educational and professional experiences in the past. As a successful professional, you will need good reflective and writing skills. Journal activities offer you the opportunity to further develop these skills. For more information about Blackboard blogs and journals, review these tutorials.

Verified Expert

The paper is about the work breakdown structure and received approval to begin scheduling the office move, the manager, Steve Spaniels, would like to review a network diagram and present it to the CEO. A project network diagram by first identified followed by calculations. It will also help in understanding the work breakdown structure and scheduling activities of project through network diagram and will also include the calculations that estimate various aspects of the project.

Reference no: EM131375912

Questions Cloud

Is bullying more serious now than with previous generations : Do you think this boy's response was appropriate? What consequences should youth who retaliate against bullies face?Is bullying more serious now than with previous generations? Support your answer. What should be done to address the issues that cau..
Was it qualitative or quantitative approach : Think back to a time in your life when you were faced with a critical decision. Describe what your decision was, and the approach you took to making it. Did you use a systematic approach? Was it a qualitative or quantitative approach? What was the ou..
Approaches to public administration paper : This assignment is worth 100 points. Your report is to be prepared as a Word document and transmitted to the instructor as a Dropbox attachment. The entire document is to be 600 to 1,000 words in length.
Create a written report with the given information : Create a written report with the following information for the small business you have selected: Name of business and business owner and Original start-up business opportunity.
Build out of the new facility : Relocate the entire office of 200 people to a new office building across town and purchase and installation of items for the new building is part of the project's responsibility - Relocate the entire office of 200 people to a new office building acro..
Evaluate the relationship between ethics and leadership : Go on to examine and critically evaluate the relationship between ethics, leadership and decision making. In conclusion, reflect critically on how leaders may ensure organisational decisions are made ethically
What is one of main reasons the rooftop unit has to be level : If the rooftop unit is subjected to a corrosive environment, and cannot be installed in an area away from the offending corrosion, what would be a possible alternative?
Linear programming is very common decision tool : Linear programming is very common decision tool used by organizations for a variety of purposes including planning business operations, portfolio optimization, and workforce planning.
Mental disturbance and delinquency : While there is evidence suggesting an association between mental disturbance and delinquency, it was pointed out that there are intervening variables that may account for the association. List and describe these factors. Do you think these factors..

Reviews

len1375912

1/30/2017 1:49:51 AM

Network Diagram Entry clearly describes the process of the network diagram including the forward/backward pass, slack/float, and critical path with specific relevant examples Synthesis Entry shows excellent evidence of synthesis of the module content and exhibits careful consideration of the topic Voice Entry is written in a style that is appealing and appropriate for the intended audience and a consistent voice is evident throughout Writing Entry is free of errors in organization and grammar

Write a Review

Project Management Questions & Answers

  Social security and self-employment

Assume Suzanne is paid a salary of $45,000. For each of the following situations, determine who is responsible for paying the Social Security and self-employment taxes on the income from the business and who is allowed a deduction for the Social S..

  Should a corporation reduce its ethical standards

When making purchasing decisions, should a corporation reduce its ethical standards in order to allow the company to compete internationally? Take a position and defend your answer.

  Computing ocf for project

The project is estimated to generate $3,100,000 in annual sales, with costs of $990,000. If the tax rate is 35%, what is the OCF for this project?

  What would be the half life of sewage

suppose some sewage drifting down a stream decomposes with a reaction rate coefficient equal to 0.2/d. - What would be the half life of sewage?how much would be left after 5 days??

  Prepare a cash-flow budget and a profit budget

This assignment will summative assess the following learning outcome: it should be able to apply and demonstrate an understanding of Various performance strategies and techniques.

  How knowledge transfer for project management

Compare how knowledge transfer for project management happens in your organization. Where can your organization make improvements to ensure knowledge transfer is a critical success area in the future

  Calculating production variable cost

Answer is following please explain how they calculated Production Variable cost 900, 2300,and 600.

  Construction project planning and controlshow the benefits

construction project planning and controlshow the benefits to the project lifecycle by commencing the planning proccess

  Microsoft project and openproj.

Microsoft Project and OpenProj.

  Prepare a summary of findings

Prepare a summary of findings that includes a description of the cultural values and business ethics dominant in the country,  The current status of this product in the country.

  Must owner have given agent written authorization

Owner orally authorized Agent to sell his house. Agent completed a sale of the house to Buyer.- Must Owner have given Agent written authorization?

  How is the information age changing the nature of pricing

Explain how discounts, geographic pricing, and other pricing tactics can be used to fine-tune the base price.- Write a memo analyzing the factors you need to consider in your decision.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd