PROBLEM

Eiffel Builders Inc enters into a contract with SupeInfrastructure to build a water desalination plant...Eifel Builders engages Aqua Engineers to prepare turbine capacity specifications for each stage. The contract provided for payment a 3-stage basis.

The specifications on three occasions are stamped "approved" by Eiffel. Subsequently Eiffel refuses to pay for the Specifications services on the basis that the speciation prepared were not adequate and involved a variation of the provisions of the contract..

At  site meeting is organised with all parties.  They discuss the requirements and verbally agree on terms to vary the construct so that the specifications as presented can be carried out   acting on this agreement the building proceeds.  A few weeks later Eiffel r refuses to pay Aqua because the specifications are not complete and do not comply with the terms of the written contract.

QUESTIONS

PART A

ASSUME THAT THE SECURITY OF PAYMENTS LEGISLATION DOES NOT APPLY

1. What is affect of a conflict between the specifications and the written terms of the contract? How do you resolve that conflict?  Address legal principles.

2. What is the legal affect of stamping the specifications "approved" on any future contractual position? Refer and explain the legal principles and describe what rights each party may have.

3. Do the parties have to act in good faith?  How these principles could be applied to the appropriate conduct of the parties

4. What procedures would you formulate to cover possible amendments of the contract in the course of construction and

5. How experts could be used in the court system in this dispute and what it their role to assist the resolution disputes. Refer  to the Expert Code of Conduct

PART B

What is the impact of the Security of Payment legislation in possible dispute resolution and if the parties in the above case wished to use the procedure provided what is required. Describe the process what each party would be required to do and refer and explain the relevant section of the act.

Write a report in 2000 words count and make proper referencing of report. Please make sure answering all above questions in report format.

Reference no: EM13869184

Questions Cloud

Importance of infrastructure projects : Describe the importance of infrastructure projects to the development of society.
Quantitative expression in the natural sciences : Outcome 1- Demonstrate the ability to understand and use quantitative expression in the natural sciences.
The intelligence methods and duties and responsibilities : Compare and contrast the intelligence methods and duties and responsibilities of the U.S. military
Analyze economic conditions that affect revenue projections : Analyze the economic conditions that affect revenue projections
Affect of a conflict between the specifications : What is affect of a conflict between the specifications and the written terms of the contract? How do you resolve that conflict?  Address legal principles.
How hard should houston press to get harris to act now : What techniques should Houston have used to overcome the forestalling tactic? How hard should Houston press to get Harris to act now
Report optimal number of full-time and part-time employee : Report the optimal number of full-time and part-time employees to work in each shift. Report the optimal cost of operating the call center. Present the results from the sensitivity analysis.
Explain the role of information sharing since 9/11 : Explain the role of information sharing since 9/11
Public sector infrastructure projects : Identify two key challenges project managers must address in public sector infrastructure projects and discuss how these challenges are similar to and different from those experienced by a project manager managing projects within a corporate envi..

Reviews

Write a Review

Project Management Questions & Answers

  Questiona i what do you know by the term delivery of a

questiona i what do you know by the term delivery of a product? ii when does delivery formally arise?iii what are

  Conducting research for your media analysis project

You selected a topic and began conducting research for your Media Analysis Project. Now it is time to use that research to formalize your thesis and create an outline for you paper. If you put in a good effort here, the act of actually writing the..

  Types of risks are inherent in a project

What types of risks are inherent in a project? Where do they originate? Can they be mitigated? How? What are the consequences of ignoring a conflict within a project team?

  Explain the organization that is in need of the pool

Explain the organization that is in need of the pool and show the expected benefits that are motivating the organization to commission this project.

  What is the pert weighted average for this activity

A project manager has received the following probabilistic estimates for the duration of an activity: optimistic duration is 7 workdays, most likely duration is 8 workdays and pessimistic duration is 15 workdays. What is the PERT weighted average ..

  Communication plan for the riordan manufacturing

Create a communication plan for the Riordan Manufacturing Go Green campaign, using the WBS and project organization chart. Write an executive summary of no more than 1,050 words in which you explain how communication plan and software will enable pr..

  Identify primary characteristics of product

Discuss the type of product the company will offer and identify its primary characteristics.

  Basic phases of project management

Construct a clear project of project management course and most important is to cover the five Basic Phases of Project Management

  The project manager and margaret is the contract manager.

Assignment: On April 8, one week before the first internal project review is scheduled to take place, Spencer Tracey and Margaret Porter are reviewing the presentation that Spencer intends to make to their vice president. Spencer is the project manag..

  Given the following information for a one-year project

given the following information for a one-year project answer the following questions recall that pv is the planned

  How would i manage this situation if i was the leader what

how would i manage this situation if i was the leader? what would i consider? what steps would i take? what would be

  Lasa project planning developing the project plan

LASA Project Planning Developing the Project Plan and Determining Critical Path

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd