Write definition of the following -

(i) Afflux. ( ii ) Free Board. ( iii ) Clearance. ( iv ) Via duct. ( v ) Skew Bridge ( vi ) Cause Way. ( vii ) Clear Span. ( viii ) Effective span. ( ix ) Over all Span ( x ) Score. ( xi ) Water Way.

Ans.- Afflux - It is the rise in the flood level of the river up stream of the bridge as a result of obstruction to natural flow caused by the construction of the bridge.

Free Board - This is the vertical distance between the high flood level inclusive of afflux and the formation level.

Clearance - This is the vertical distance between the high flood level inclusive of afflux and the bottom most part of bridge super structure like slab girder etc.

Via duct - When the bridge is constructed to cross a valley for railway instead of filling it the bridge as called via duct.

Skew Bridge - When the bridge is not right angle to the axis of river or other such opening it is called a skew bridge.

Cause Way - It is a bridge constructed to pass a flood water over the railway track is called cause way.

Clear Span - It is the clear distance between any two bridge supports like abutments piers etc. Effective span - It is the distance between centers of two adjacent bridge supports.

Over all Span - It is the over all length of girder.

Score - It is the rise in the distance from rail level and bottom of rivers.

Water Way - The area of the opening of a bridge blow super structure through which water flows is called water way.


Related Discussions:- Write definition of afflux and skew bridge

Show the excessive movement joints in bridges, Q. Show the Excessive moveme...

Q. Show the Excessive movement joints in bridges? Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from

Minimum volume of sump volume for pumps, Minimum volume of sump volume for ...

Minimum volume of sump volume for pumps Maximum pumping rate = Q P Volume of sump = V Inflow Rate = Q i Cycle Time T c = t 1 + t 2 t 1 = V / Q P - Q i t 2

Compacted thickness of bituminous pavement, Q. Compacted thickness of bitum...

Q. Compacted thickness of bituminous pavement? The choice of compacted thickness is closely related to the nominal maximum size of aggregates of bituminous materials. Based on

Bearings, what is the difference between whole circle bearing and reduced b...

what is the difference between whole circle bearing and reduced bearing?

Distomat, definition,old&new modern&difference

definition,old&new modern&difference

Define the approach velocity, Define the Approach Velocity Typical prob...

Define the Approach Velocity Typical problems have negligible approach velocity.  v 1 = Q/A, where A = the cross-sectional area of flow in the channel. The value is not the ve

Timber, What is exogenous tree?

What is exogenous tree?

Foundation, why is the foundation failure?

why is the foundation failure?

Define superposition method, Define Superposition Method  1. Remove eno...

Define Superposition Method  1. Remove enough redundant supports to reduce the structure to a statically determinate condition 2. Calculate the deflections at the previous l

Explain fluidized-bed incinerators, Explain Fluidized-Bed Incinerators ...

Explain Fluidized-Bed Incinerators sand is heated to 800C by oil or gas and blown around (fluidized) by a blower that sends air from bottom upward heated fluidized san

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd