Write definition of afflux and skew bridge, Civil Engineering

Assignment Help:

Write definition of the following -

(i) Afflux. ( ii ) Free Board. ( iii ) Clearance. ( iv ) Via duct. ( v ) Skew Bridge ( vi ) Cause Way. ( vii ) Clear Span. ( viii ) Effective span. ( ix ) Over all Span ( x ) Score. ( xi ) Water Way.

Ans.- Afflux - It is the rise in the flood level of the river up stream of the bridge as a result of obstruction to natural flow caused by the construction of the bridge.

Free Board - This is the vertical distance between the high flood level inclusive of afflux and the formation level.

Clearance - This is the vertical distance between the high flood level inclusive of afflux and the bottom most part of bridge super structure like slab girder etc.

Via duct - When the bridge is constructed to cross a valley for railway instead of filling it the bridge as called via duct.

Skew Bridge - When the bridge is not right angle to the axis of river or other such opening it is called a skew bridge.

Cause Way - It is a bridge constructed to pass a flood water over the railway track is called cause way.

Clear Span - It is the clear distance between any two bridge supports like abutments piers etc. Effective span - It is the distance between centers of two adjacent bridge supports.

Over all Span - It is the over all length of girder.

Score - It is the rise in the distance from rail level and bottom of rivers.

Water Way - The area of the opening of a bridge blow super structure through which water flows is called water way.


Related Discussions:- Write definition of afflux and skew bridge

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

Main advantages of using rubber dams, Question In assortment of dams in...

Question In assortment of dams in drainage channels, what are the main advantages of using rubber dams instead of steel-gate dams ? Answer Key Advantages of rubber d

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

survey, what is fore bearing and back bearin

what is fore bearing and back bearing

Enumerate the term - failure due to crushing of concrete, Enumerate the ter...

Enumerate the term - Failure Due to Crushing of Concrete Over reinforced pre-stressed concrete members, provided with a large amount of pre-stressing steel or relatively small

Passenger conveyors, Passenger Conveyors: Passenger conveyors are used...

Passenger Conveyors: Passenger conveyors are used at locations where a large concentration of passengers has to be moved from one place to another. Escalators are used to conv

Roads in deserts, Roads in Deserts: Problems Encountered The ...

Roads in Deserts: Problems Encountered The western portion of Rajasthan is part of the Thar desert, where strong winds below the fine desert sand particles leading to

Stone soling - road pavements, Stone Soling: One of the early practic...

Stone Soling: One of the early practices in road construction was to provide a stone soling 150-225 mm in thickness. The stones are laid by manual labour, and stone spalls ar

On-line storage vs. off-line storage, On-line storage vs. off-line storage ...

On-line storage vs. off-line storage Design of storage pond is commonly divided into off -line storage and on-line storage. The on-line storage concept includes inclusion of s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd