What are the disadvantages of bottom-up decentralised, Project Management

What are the disadvantages of bottom-up decentralised approaches?

Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager or project team sets the budget.

The disadvantages top-down decentralised approaches:

a. Budgetary 'slack' or 'padding' or 'buffering' for example over estimation of costs assigned by participants 'just in case' over spending does arise. This leads to incompetent allocation of finance

b. Financial inexperience of project management and team

c. Slower process to formulate a budget since greater consultation needed.

 

Posted Date: 8/31/2013 7:32:38 AM | Location : United States







Related Discussions:- What are the disadvantages of bottom-up decentralised, Assignment Help, Ask Question on What are the disadvantages of bottom-up decentralised, Get Answer, Expert's Help, What are the disadvantages of bottom-up decentralised Discussions

Write discussion on What are the disadvantages of bottom-up decentralised
Your posts are moderated
Related Questions
1. Inventory  and Stores Control : Inventory  control is  a systematic procedure  for  ensuring  the  availability  of items necessary to meet the  production  requirements  at o

Project manager and project team The project board will ultimately choose whether changes are executed or not and it will then be the responsibility of the project manager to m

Define the Resource Histograms in short. Resource histograms A resource histogram is a column (or bar) chart which demonstrates the number of resources allocated to a pro



For this unit (Computer Project), you are required to plan, analyse, design, implement, test, document and demonstrate a prototype of your choice.  Once you have identified a fo

S catter diagrams The possible relationships between two variables are identified using scatter diagrams. In order to understand data as a whole, it is very important to under

Q. Show the product formulation? One should also see the kind of infrastructure available in the laboratory and use the techniques which can be easily standardized for example,

QUESTION a) Major project management activities have their operational specificities. List the distinguishing characteristics of a project? b) Project management faces a lot

A highly sensitive device used to measure electricity activity in the brain is required to have a variance in measurements not exceeding 0.0001 volts^2. if the variance exceeds thi