Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Project execution plan, A project execution plan (written and graphical rep...

A project execution plan (written and graphical report) developing the strategy covering FIVE key areas: Some guidelines for each subject area are listed below, but the report s

Define the term scenario planning in risk management, Define the term Scena...

Define the term Scenario Planning in risk management. Scenario planning: It is about perceiving uncertainties for example identification of risks and the growth of pre-em

Prepare a proper memo addressed to bill, You are an accountant who has been...

You are an accountant who has been approached by two people, Bill and Steve, for some advice.  Bill and Steve are planning to open a furniture store in Toronto.  They plan to rent

Family planning research center of nigeria, 1. Some of the tasks in this pr...

1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the proj

What is the meaning of exception reports, What is the meaning of exception ...

What is the meaning of exception reports? Progress (or exception reports) can be utilized to monitor and to control the project. It permits the project board or project manager

Benefits of having a project and programme support office, What are the ben...

What are the benefits to an organisation of having a Project and Programme support office? The major advantages to an organisation by having a Project and Programme support off

Produce a management report of a company, There are two learning objectives...

There are two learning objectives of this assessment. 1. The first relates directly to the operations management materials presented in the lectures 4 and 5. This assessment wil

Project management, • What do you consider are the leadership skills requir...

• What do you consider are the leadership skills required of a project manager in relation to the processes involved in managing complex projects? • In any project it is important

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd