Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Develop a project concept, • Develop a project concept. Find a stakeholder ...

• Develop a project concept. Find a stakeholder who will act as sponsor for the project. Outline the business problem that the system is intended to address, and establish an initi

Explain the gantt charts in risk management, Explain the Gantt Charts in ri...

Explain the Gantt Charts in risk management. Gantt Charts: By Henry Gantt a time chart devised into 1917s, an American engineer. This chart is a horizontal bar chart ut

Growth in outsourcing by organisations, Briefly explain the reasons for the...

Briefly explain the reasons for the growth in outsourcing by organisations. Outsourcing involves the contracting out of a business function to an external third partyprovider.

Projectplanning, #question.what is project planning.

#question.what is project planning.

What is a project life cycle, Q. What is a project life cycle? If a pro...

Q. What is a project life cycle? If a project is well prearranged it will progress logically through several phases. There are four standard stages to a typical project. The fi

Total quality management approach within 2jn, 2JN is a large manufacturing ...

2JN is a large manufacturing organisation which is structured with a number of supervisors every responsible for their own work production unit. Supervisors report to a team of sen

Project Management Organization Framework, The Big Dig has often been criti...

The Big Dig has often been critiqued due to costs and challenges. To what extent do you think is it possible to identify risks associated with the project early in the project''s l

What is organizational culture and its characteristics , Organization's cul...

Organization's culture is the shared perception that organizational members have about its characteristics.As stated earlier, an organization's competitive advantage depends largel

How are carrying costs varied with quantity order, How are carrying costs v...

How are carrying costs varied with quantity order? Carrying Costs, that vary along with quantity ordered, contained as a. There Interest on capital investment b. There Co

Explain the tool of total quality improvement, Question: As the Managin...

Question: As the Managing Director of your organization, you have been analyzing other institutions that you regard as competitors. Extrapolating your current position up to t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd