Unit rate contracts , Project Management

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  

Posted Date: 9/27/2012 8:02:33 AM | Location : United States







Related Discussions:- Unit rate contracts , Assignment Help, Ask Question on Unit rate contracts , Get Answer, Expert's Help, Unit rate contracts Discussions

Write discussion on Unit rate contracts
Your posts are moderated
Related Questions
Define the term Scenario Planning in risk management. Scenario planning: It is about perceiving uncertainties for example identification of risks and the growth of pre-em

Notice how you would organise your project team for RAD-type project. What leadership practices would this need by the project leader and what would the team members have to perfor

Communication Strategy: Communication strategy, beginners as a concept in the 1980s by communication expert Mary Munter, provides as the basis for all management communic

Greeting, Do you use Microsoft Project Management software for project management assignments if needed

Quality is customer defined: Quality of service or service excellence is a desire to maintain or strengthen the commitment to the library's philosophy of service to users. Qua

Illustrate an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Precede

Q. Why do projects always seem to cost more than expected? In general this seems to stem from three causes. The first may merely be an overly optimistic cost estimate. Sometime

Question 1: a) Outline the key responsibilities of an Event Manager b) Give THREE clear working examples of possible event objectives for either a country, a resort, an or

From what product must the acceptance criteria for a project is derived and why? The acceptance criteria must be derived by the Requirements Specification that is where the use

Develop a work breakdown structure. 3. Make a list of the specific activities that need to be done between now and the wedding day. 4. For each activity, identify the person (Tony,