The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Market share in a high market growth industry, R Company produces a range o...

R Company produces a range of hair and beauty products. T, the Finance Director, and P, the Marketing Director, are reviewing the outcome of some product portfolio analysis which h

Describe problems with functional project coordination, Question 1: "Ma...

Question 1: "Matrix structures are becoming more common and are likely to continue to do so in the future" (Field and Keller, 1998). a) Describe likely problems with functio

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

Project, can make two project for me?

can make two project for me?

Determine the best practices apply to project implementation, The objective...

The objectives of assignment are to determine what best practices apply to project implementation and close out, and to apply your individual knowledge of the quantitative topics t

Different strategies that lg use to manage the conflict, LG, the Managing D...

LG, the Managing Director of NWP Company, recently announced to the workforce that the Board had agreed to the establishment of a set of new working practices which should lead to

Relationship between project manager and project team, Project manager and ...

Project manager and project team The project board will ultimately choose whether changes are executed or not and it will then be the responsibility of the project manager to m

Project risk custodians , Project risk custodians  The quality risk fun...

Project risk custodians  The quality risk function is carried out by the project risk custodians. The responsibility of project risk custodians is to:    Integrate all po

What are the processes of producing budgets, What are the processes of prod...

What are the processes of producing budgets? The process of producing budgets: • A budget manual is formed to provide instructions, delegate responsibilities, reporting line

Electronic document delivery systems, Electronic Document Delivery Systems:...

Electronic Document Delivery Systems: The systems employing electronic technology for the receipt of requests and supply of documents are known as Electronic Document Delivery

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd