Identify the critical path by activities and duration, Project Management

Assignment Help:

Identify the critical path by activities and duration.

Activity          Duration (Wks)       Preceded by

A                     5                               -

B                     6                               -

C                     2                               A, B

D                     1                               C

E                     3                                C

F                     4                                C

G                     5                              D, E, F

Identify the critical path of above given activities and calculate what the elapsed time of the project would be? Determine the numbers of weeks to activity D over run by without affecting the elapsed time of the project?


Related Discussions:- Identify the critical path by activities and duration

Structure of people management system, Question 1: Explain the force Co...

Question 1: Explain the force Content and Structure of People Management System Explanation of structure Explanation of content Balance between content and struct

Communication-coordination beneficial in project management, How are commun...

How are communication and coordination beneficial in project management software? Communication and coordination: Project software can give automatic report templates al

Project specification and planning, Industrial Design Industrial Desig...

Industrial Design Industrial Design differs from conventional design engineering in terms of (largely) aesthetic and ergonomic requirements, coupled with a need for effective

Explain the gantt charts in risk management, Explain the Gantt Charts in ri...

Explain the Gantt Charts in risk management. Gantt Charts: By Henry Gantt a time chart devised into 1917s, an American engineer. This chart is a horizontal bar chart ut

Operating characteristic curve, O perating characteristic curve The op...

O perating characteristic curve The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage de

What does positive and negative npv indicate, Net Present Value (NPV) analy...

Net Present Value (NPV) analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflow and outflow to the

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

Work breakdown structure, I have a project that I would like to have a work...

I have a project that I would like to have a work breakdown structure developed for.

Can surprises be reduced, Q. Can surprises be reduced? Yes absolutely! ...

Q. Can surprises be reduced? Yes absolutely! By their vary nature projects are uncertain business and uncertainty can lead to both risk and opportunities. As a result a very im

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd